Location Mile Marker Severity Closure Details Time Periods Source Description
Black Rd (+0.4 miles) to CR-J (-0.2 miles) 113.9 to 115.5 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/28/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA
Entrance ramp from SB US-151 136.2 Major Various lanes closed 4/26/15 7:00 PM to 4/27/15 6:00 AM daily until 5/22/15 WisDOT Construction - Detour: USH 151S, Exit 97B N/W IH39/90/94, Exit 132 USH 51S, On Ramp S/E IH 39/90/94
IL-173 (West Lane Rd) (+1.6 miles) to Harlem Rd (+0.7 miles) 10.5 to 11.5 Medium Right lane closed, two lanes open 4/27/15 12:01 PM to 2:00 PM Illinois Tollway Moving Operation; Pavement Coring
Sleepy Hollow Rd (+0.4 miles) to River Rd (-0.1 miles) 53.7 to 55.5 Medium Left lane closed, two to 7 lanes open 4/27/15 9:00 AM to 7:00 PM Illinois Tollway Rdwy Widening and Reconst
Meacham Rd (-0.4 miles) to Meacham Rd (+0.1 miles) 67.0 to 67.5 Medium Left lane closed, three lanes open 4/26/15 8:00 PM to 10:00 PM Illinois Tollway Rdwy/Bridge Reconst
Meacham Rd (-0.4 miles) to Meacham Rd (+0.1 miles) 67.0 to 67.5 Medium Left two lanes closed, two lanes open 4/26/15 10:00 PM to 4/27/15 5:00 AM Illinois Tollway Rdwy/Bridge Reconst
I-290 (+0.3 miles) to IL-58 (-0.5 miles) 68.5 to 68.9 Medium Right lane closed, two or three lanes open 4/27/15 7:00 AM to 4:00 PM Illinois Tollway Retaining/Noise Wall and Draining Improv; (Right lane of CD road to I-290 / IL-53 closed)
Exit ramp to NB IL-53 None All lanes and shoulders open 4/23/15 7:00 AM to 5/8/15 11:59 PM Illinois Tollway Left Side of Ramp Closed; *** Long Term Closures ***
Entrance ramp from NB IL-53 Local 68.8 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from NB Elmhurst Rd 73.8 Medium All lanes and shoulders closed 4/23/15 7:00 AM to 6/30/15 11:59 PM Illinois Tollway *** Long Term Closure ***
Ramp from EB I-90 to Cumberland Ave / IL-171 79.3 Minor Partial closure 11/25/14 7:00 AM to 4/30/15 11:59 PM IDOT ***Long Term Closure***
Cumberland Ave (IL-171) to Harlem Ave (IL-43) 79.6 to 81.2 Minor Right shoulder closed, all lanes open 4/27/15 9:00 AM to 3:00 PM IDOT Moving Operation
Cumberland Ave (IL-171) to Eisenhower Expy (I-290) 79.6 to 51.6 None Right shoulder closed, all lanes open 4/26/15 11:00 PM to 4/27/15 5:00 AM IDOT Moving Operation
Lawrence Ave to Jackson Blvd 84.1 to 51.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/27/15 9:00 AM to 3:00 PM IDOT Moving Operation
Kennedy (I-90/94) to Orleans St 50.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/26/15 11:00 PM to 4/27/15 5:00 AM IDOT Moving Operation
Exit ramp to WB I-290 51.4 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Jackson Blvd to Eisenhower Expy (I-290) 51.5 to 51.6 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to Harrison St 51.6 to 51.7 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Entrance ramp from EB Eisenhower / I-290 52.0 Minor Right lane and both shoulders closed, up to two lanes open 6/22/14 12:00 AM to 5/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Entrance ramp from WB I-290 52.0 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Taylor St to 26th St 52.1 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/27/15 10:00 AM to 1:00 PM IDOT Moving Operation
Taylor St to I-57 / Bishop Ford (I-94) 52.1 to 62.9 Minor Both shoulders closed, all lanes open with partial ramp closures 4/27/15 9:00 AM to 3:00 PM IDOT Moving Operation
26th St to 63rd St 54.1 to 58.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/27/15 9:00 AM to 1:30 PM IDOT Moving Operation
Cermak Rd (22nd St) to Dan Ryan Expy (I-94) 54.6 Minor Both shoulders closed, all lanes open with partial ramp closures 4/27/15 9:00 AM to 3:00 PM IDOT Moving Operation
63rd St to Wentworth Ave 58.7 to 58.9 Medium Left lane and left shoulder closed, one to three lanes open 3/31/15 12:00 AM to 8/31/15 11:59 PM IDOT ***Long Term Closure***
at Exit to SB Chicago Skwy 58.8 Medium Left lane and left shoulder closed, three lanes open 3/31/15 8:00 AM to 8/31/15 11:59 PM IDOT ***Long Term Closure***
150th St to US-20 6.0 to 7.0 None All lanes and shoulders open 4/9/15 7:00 AM to 11/18/15 11:59 PM Indiana Toll Road Maximum Width of 11 ft. and Maximum Weight of 120,000 lbs.
at Knights Of Columbus Dr 6.5 Medium Right lane closed, one lane open 4/11/15 12:00 AM to 6/1/15 11:59 PM Indiana Toll Road Bridge Rehabilitation
700 West (+0.5 miles) to CR-935 (+0.4 miles) 114.0 to 156.9 Medium Right lane closed, one lane open 4/27/15 7:00 AM to 3:00 PM Indiana Toll Road Moving Operation; Pothole Patching

I-90 Express EB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
26th St to 69th St 54.1 to 59.5 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/27/15 9:00 AM to 1:30 PM IDOT Moving Operation
Cermak Rd (22nd St) to Dan Ryan Expy (I-94) 54.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/27/15 9:00 AM to 3:00 PM IDOT Moving Operation

I-90 Express WB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
69th St to 26th St 59.5 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/27/15 10:00 AM to 3:00 PM IDOT Moving Operation

I-90 Reversible EB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
Ogden Ave to Montrose Ave Major All lanes and shoulders closed 4/26/15 11:00 PM to 4/27/15 1:00 AM IDOT

I-90 Reversible WB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
Ogden Ave to Montrose Ave Major All lanes and shoulders closed 4/26/15 11:00 PM to 4/27/15 1:00 AM IDOT

I-90 WB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
CR-935 (-0.4 miles) to 700 West (-0.6 miles) 156.9 to 114.0 Medium Right lane closed, one lane open 4/27/15 7:00 AM to 3:00 PM Indiana Toll Road Moving Operation; Pothole Patching
Exit ramp to I-94 21.0 Major All lanes and shoulders closed 3/18/15 7:00 AM to 11/15/15 11:59 PM Indiana Toll Road Lake Station exit ramp closed for Ramp Demo/Rebuild ***Long Term***
Entrance ramp from I-80/I-94 20.4 Major All lanes and shoulders closed 3/18/15 8:00 AM to 6/29/15 11:59 PM Indiana Toll Road Lake Station entrance ramp closed for Bridge Demo/Rebuild for 13 weeks ***Long Term Closure***
US-20 to 150th St 7.0 to 6.0 None All lanes and shoulders open 4/9/15 7:00 AM to 11/18/15 11:59 PM Indiana Toll Road Maximum Width of 11 ft. and Maximum Weight of 120,000 lbs.
I-57 / Bishop Ford (I-94) to Taylor St 62.9 to 52.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/27/15 9:00 AM to 3:00 PM IDOT Moving Operation
63rd St to 26th St 58.7 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/27/15 10:00 AM to 3:00 PM IDOT Moving Operation
Stevenson Expy (I-55) to Eisenhower Expy (I-290) 53.7 to 51.7 Medium Right lane and right shoulder closed, two to four lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from NB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from SB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to EB I-290 52.4 Major All lanes and shoulders closed 3/13/15 12:00 AM to 12/31/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to WB I-290 52.4 Minor Both shoulders closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT Reduced width ***Long Term Closure***
Roosevelt Rd to Eisenhower Expy (I-290) 52.2 to 51.7 Minor Both shoulders closed, all lanes open 3/13/15 12:00 AM to 6/1/16 11:59 PM IDOT Lanes shifted. 4 lanes total through section ***Long Term Closure***
Entrance ramp from Roosevelt Rd 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from Taylor St 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Eisenhower Expy (I-290) to Jackson Blvd 51.7 to 51.5 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to I-190 51.7 to 79.1 None Right shoulder closed, all lanes open 4/26/15 11:00 PM to 4/27/15 5:00 AM IDOT Moving Operation
Jackson Blvd to Lawrence Ave 51.5 to 84.2 Minor Both shoulders closed, all lanes open with partial ramp closures 4/27/15 9:00 AM to 3:00 PM IDOT Moving Operation
Kennedy (I-90/94) to Orleans St 50.3 Minor Both shoulders closed, all lanes open with partial ramp closures 4/26/15 11:00 PM to 4/27/15 5:00 AM IDOT Moving Operation
Orleans St to Kennedy (I-90/94) 50.3 Minor Both shoulders closed, all lanes open with partial ramp closures 4/26/15 11:00 PM to 4/27/15 5:00 AM IDOT Moving Operation
at Devon Plaza 77.2 to 77.1 None All lanes and shoulders open with partial ramp closures 4/23/15 7:00 AM to 7/31/15 11:59 PM Illinois Tollway Rdwy/Bridge Reconst; Right Cash Departure Lane Closed; *** Long Term Closures ***
Exit ramp to NB Elmhurst Rd 73.8 Medium All lanes and shoulders closed 4/23/15 7:00 AM to 6/30/15 11:59 PM Illinois Tollway *** Long Term Closure ***
Entrance ramp from SB Arlington Heights Rd 70.2 Minor Various lanes closed 4/23/15 7:00 AM to 11/20/15 11:59 PM Illinois Tollway Right IPO Lane Closed; Right Side of Ramp Closed; *** Long Term Closures ***
Exit ramp to SB IL-53 Medium Left lane closed, one lane open 3/17/15 7:00 AM to 8/1/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst; (Left lane of CD road to IL-290 / IL-53 closed); *** Long Term Closure ***
Entrance ramp from SB IL-53 67.6 Minor Partial closure 4/3/15 12:00 AM to 8/1/15 12:00 AM Illinois Tollway Rdwy Widening and Reconst; Right Side Ramp closed; ***Long Term Closure***
Meacham Rd (-0.1 miles) to Meacham Rd (+0.4 miles) 67.5 to 67.0 Medium Left lane closed, three lanes open 4/26/15 8:00 PM to 10:00 PM Illinois Tollway Rdwy/Bridge Reconst
Meacham Rd (-0.1 miles) to Meacham Rd (+0.4 miles) 67.5 to 67.0 Medium Left two lanes closed, two lanes open 4/26/15 10:00 PM to 11:00 PM Illinois Tollway Rdwy/Bridge Reconst
Meacham Rd (-0.1 miles) to Meacham Rd (+0.4 miles) 67.5 to 67.0 Medium Left three lanes closed, one lane open 4/26/15 11:00 PM to 4/27/15 5:00 AM Illinois Tollway Rdwy/Bridge Reconst; FOUR (4) 15 minute FULL CLOSURES with Trooper Assistance at 11:30pm, 12:00am, 12:30am and 1:00am
Exit ramp to Roselle Rd 66.0 Minor Partial closure 6/17/14 5:00 AM to 6/6/15 11:59 PM Illinois Tollway ***Long Term Closure***; Right IPO Lane Closed
Exit ramp to NB Roselle Rd 66.0 None Partial closure 4/17/15 7:00 AM to 8/1/15 11:59 PM Illinois Tollway Right Side of Ramp Closed; *** Long Term Closure ***
Beverly Rd (+0.1 miles) to Beverly Rd (+0.8 miles) 58.1 to 57.4 Medium Right lane closed, two lanes open 4/26/15 5:00 AM to 7:00 PM Illinois Tollway Rdwy and Bridge Widening
Beverly Rd (+0.1 miles) to Beverly Rd (+0.8 miles) 58.1 to 57.4 Medium Right lane closed, two lanes open 4/26/15 7:00 PM to 4/27/15 5:00 AM Illinois Tollway Rdwy and Bridge Widening
Spring Creek Rd (+0.9 miles) to E. Riverside Rd (+0.8 miles) 12.5 to 11.5 Medium Right lane closed, two lanes open 4/27/15 8:00 AM to 11:00 AM Illinois Tollway Moving Operation; Pavement Coring
CR-J (+0.1 miles) to Kent Rd 115.5 to 114.3 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/28/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

Site Contributors | Policies | Disclaimer | Glossary | Contact Us
Please send comments, suggestions, or requests for help to Travel Midwest webmaster.
Much of this site's functionality makes use of cookies and JavaScript.
Sun Apr 26 2015 15:57:17 CDT