Construction Report
Select Location
  
Updated: 4/1/15 9:17 AM

Reports Help

Use these links to view other reports for the selected location: travel times / incidents / construction / special events / congestion / dynamic message signs / cameras / detectors

NOTE: You may place the mouse over a location to see its municipality and county, or click on the location to see a map of the event.

Construction information transmitted by the Illinois Tollway for display on the I-90 EB, I-90 WB, I-94 EB, I-94 WB, I-294 NB, I-294 SB, Edens Spur EB, Edens Spur WB, Jane Addams Memorial (Northwest) EB, Jane Addams Memorial (Northwest) WB, Tri-State NB/WB and Tri-State SB/EB reports of the Travel Midwest website does not include "shoulder only" projects. For more information on "shoulder only" closures, please visit the Tollway website at www.illinoistollway.com.

I-55 NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Reed Rd to Lake Shore Dr (US-41) 233.5 to 293.7 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
IL-59 to Jefferson St (US-52) 251.6 to 252.8 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to SB IL-171 282.1 Minor All lanes and shoulders closed 3/30/15 7:00 AM to 10/31/15 11:59 PM IDOT ***Long Term Closure***
Exit ramp to NB Dan Ryan Expy 291.5 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***

I-55 SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Lake Shore Drive to Reed Rd 293.9 to 233.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to NB Dan Ryan Expy 292.9 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to SB IL-171 282.8 Major All lanes and shoulders closed 3/30/15 12:00 AM to 10/31/15 11:59 PM IDOT Long Term Closure
0.5 miles north of County Line Rd to 0.5 miles south of County Line Rd 276.9 to 275.9 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to SWB Joliet Rd 269.7 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT

I-57 NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
1.0 miles south of Stuenkel Rd to 1.0 miles north of Stuenkel Rd 336.1 to 338.1 Minor Left shoulder closed, all lanes open 3/19/15 12:00 AM to 4/1/15 11:59 PM IDOT ***Long Term Closure***
Steger Rd to Dan Ryan Expy (I-94) 338.1 to 357.8 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 2:00 PM IDOT Moving Operation

I-57 SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Dan Ryan Expy (I-94) to I-80 358.0 to 344.8 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:00 PM IDOT Moving Operation
I-80 to 1.0 miles north of Steger Rd 344.8 to 339.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 8:30 AM to 12:30 PM IDOT Moving Operation
1.0 miles north of Stuenkel Rd to 1.0 miles south of Stuenkel Rd 338.1 to 336.1 Minor Right shoulder closed, all lanes open 3/19/15 12:00 AM to 4/1/15 11:59 PM IDOT ***Long Term Closure***

I-80 EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Mississippi River to IL-84 0.0 to 0.3 Medium Various lanes closed 3/20/15 7:00 AM to 4/14/15 7:00 PM IDOT One direction at a time will be closed to all traffic for 4 days from Friday night at 8:00 PM until Tuesday. There will be a total of two closures, one in each direction. We will not close over the Easter weekend. --Westbound I-80 Rock Closed - No permits - Effective March 27 through March 31, 2015 --Westbound I-80 Rock Closed - No permits - Effective April 10 through April 14, 2015 --Eastbound I-80 Road Closed - No permits - Effective April 10 through April 14, 2015 --Eastbouhd I-80 Road Closed - No permits - Effective April 17 through April 21, 2015
Kendall County Line to Harlem Ave (IL-43) 122.6 to 148.8 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to NB Harlem Ave 148.9 Minor Partial closure 3/31/14 12:00 AM to 12/1/15 11:59 PM IDOT ***Long Term Closure***
Bishop Ford Fwy (IL-394) to IN State Line Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 2:00 PM IDOT Moving Operation

I-80 WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
IN State Line to Bishop Ford Fwy (IL-394) Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:30 AM to 2:30 PM IDOT Moving Operation
Harlem Ave (IL-43) to Kendall County Line 148.8 to 122.6 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
IL-84 to Mississippi River 0.3 to 0.0 Medium Various lanes closed 3/20/15 7:00 AM to 4/14/15 7:00 PM IDOT One direction at a time will be closed to all traffic for 4 days from Friday night at 8:00 PM until Tuesday. There will be a total of two closures, one in each direction. We will not close over the Easter weekend. --Westbound I-80 Rock Closed - No permits - Effective March 27 through March 31, 2015 --Westbound I-80 Rock Closed - No permits - Effective April 10 through April 14, 2015 --Eastbound I-80 Road Closed - No permits - Effective April 10 through April 14, 2015 --Eastbouhd I-80 Road Closed - No permits - Effective April 17 through April 21, 2015

I-88 EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
US-30 (Rock Falls) to US-52 (Chicago Ave) (+0.2 miles) 44.2 to 55.2 Medium Various lanes closed 4/1/15 8:00 AM to 2:00 PM Illinois Tollway
IL-23 (4th St) to IL-23 (4th St) (+0.8 miles) 92.5 to 93.3 Medium Left lane closed, one lane open 4/1/15 8:00 AM to 6:00 PM Illinois Tollway Utility Work

I-88 WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Exit ramp to IL-59 123.7 Minor Partial closure 12/16/14 7:00 AM to 6/1/15 11:59 PM Illinois Tollway Right Side Ramp closed; ***Long Term Closure***
Peace Rd (+0.7 miles) to IL-23 (4th St) 93.3 to 92.5 Medium Left lane closed, one lane open 4/1/15 8:00 AM to 6:00 PM Illinois Tollway Utility Work
Burkett Rd (+0.8 miles) to US-30 (+0.2 miles) 55.2 to 44.0 Medium Various lanes closed 4/1/15 8:00 AM to 2:00 PM Illinois Tollway

I-90 EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Bartlett Rd to IL-72 (+0.3 miles) 60.4 to 61.7 Medium Right lane closed, two lanes open 4/1/15 9:00 AM to 7:00 PM Illinois Tollway Rdwy/Bridge Widening and Reconst
Entrance ramp from SB IL-53 Local 67.6 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from NB IL-53 Local 68.8 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from NB Elmhurst Rd 73.8 Medium All lanes and shoulders closed 9/8/14 12:00 AM to 6/30/15 12:00 AM Illinois Tollway Bridge Construction; ***Long Term Closure***
Ramp from EB I-90 to Cumberland Ave / IL-171 79.3 Minor Partial closure 11/25/14 7:00 AM to 4/30/15 11:59 PM IDOT ***Long Term Closure***
at Cumberland Ave (IL-171) 79.6 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
0.5 miles east of East River Rd to Eisenhower Expy (I-290) 79.6 to 51.6 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Ohio Feeder to Grand Ave 50.3 to 50.5 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Entrance ramp from WB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to WB I-290 51.4 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Jackson Blvd to Eisenhower Expy (I-290) 51.5 to 51.6 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to Harrison St 51.6 to 51.7 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to 26th St 51.6 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Entrance ramp from EB Eisenhower / I-290 52.0 Minor Right lane and both shoulders closed, up to two lanes open 6/22/14 12:00 AM to 5/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Entrance ramp from WB I-290 52.0 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
26th St to 0.5 miles north of Chicago Skwy (I-90) 54.1 to 58.3 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation
63rd St to Wentworth Ave 58.7 to 58.9 Medium Left lane and left shoulder closed, one to three lanes open 3/31/15 12:00 AM to 8/31/15 11:59 PM IDOT Long Term Closure
Ramp from SB Dan Ryan Local to SB Chicago Skwy 58.8 to 59.3 Medium Left lane and left shoulder closed, one lane open 3/31/15 12:00 AM to 8/31/15 11:59 PM IDOT Long Term Closure

I-90 Express EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
26th St to 69th St 54.1 to 59.5 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation

I-90 Express WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
69th St to 26th St 59.5 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation

I-90 WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Marquette Rd (67th St) to 63rd St 59.3 to 58.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
63rd St to 57th St 58.7 to 58.0 Medium Right lane and right shoulder closed, two lanes open 4/1/15 10:00 AM to 2:00 PM IDOT
Garfield Blvd (55th St) to 26th St 57.7 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
26th St to Stevenson Expy (I-55) 54.1 to 53.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Stevenson Expy (I-55) to Eisenhower Expy (I-290) 53.7 to 51.7 Medium Right lane and right shoulder closed, two to four lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from NB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from SB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to EB I-290 52.4 Major All lanes and shoulders closed 3/13/15 12:00 AM to 12/31/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to WB I-290 52.4 Minor Both shoulders closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT Reduced width ***Long Term Closure***
Roosevelt Rd to Eisenhower Expy (I-290) 52.2 to 51.7 Minor Both shoulders closed, all lanes open 3/13/15 12:00 AM to 6/1/16 11:59 PM IDOT Lanes shifted. 4 lanes total through section. ***Long Term Closure***
Entrance ramp from Roosevelt Rd 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from Taylor St 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Eisenhower Expy (I-290) to Jackson Blvd 51.7 to 51.5 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to I-190 51.7 to 79.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Grand Ave to Ohio Feeder 50.5 to 50.4 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to NB Elmhurst Rd 73.8 Medium All lanes and shoulders closed 9/8/14 12:00 AM to 6/30/15 12:00 AM Illinois Tollway Bridge Construction; ***Long Term Closure***
Entrance ramp from SB Arlington Heights Rd 70.2 Minor Various lanes closed 3/23/15 7:00 AM to 11/20/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst;Right IPO Lane Closed; Right Side of Ramp Closed; ***Long Term Closure***
I-290 (-0.3 miles) to Meacham Rd (-0.1 miles) 68.5 to 67.5 Medium Left lane closed, two or three lanes open 3/17/15 7:00 AM to 8/1/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst; (Left lane of CD road to IL-290 / IL-53 closed); *** Long Term Closure ***
Ramp from WB I-90 to SB I-290/IL-53 68.3 to 68.2 Medium Left lane closed, two lanes open 3/31/15 7:00 AM to 4/14/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst; *** Long Term Closure ***
Entrance ramp from SB IL-53 Local 67.6 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from NB IL-53 Local 68.8 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Exit ramp to Roselle Rd 66.0 Minor Partial closure 6/17/14 5:00 AM to 6/6/15 11:59 PM Illinois Tollway ***Long Term Closure***; Right IPO Lane Closed

I-94 EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Entrance ramp from WB IL-132 8.3 Minor Right lane closed, one lane open 3/9/15 12:00 AM to 5/1/15 12:00 AM Illinois Tollway Rdwy Reconst. and Plaza Repairs; Right Side Ramp closed; ***Long Term Closure***
Entrance ramp from EB IL-132 8.1 Minor Partial closure 3/6/15 7:00 AM to 5/1/15 11:59 PM Illinois Tollway Right Side of Ramp Closed; ***Long Term Closure***
Park Ave West to Kennedy Junction 23.1 to 43.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB Peterson Ave 41.3 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
0.5 miles east of East River Rd to Eisenhower Expy (I-290) 79.6 to 51.6 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Ohio Feeder to Grand Ave 50.3 to 50.5 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Entrance ramp from WB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to WB I-290 51.4 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Jackson Blvd to Eisenhower Expy (I-290) 51.5 to 51.6 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to Harrison St 51.6 to 51.7 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to 26th St 51.6 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Entrance ramp from EB Eisenhower / I-290 52.0 Minor Right lane and both shoulders closed, up to two lanes open 6/22/14 12:00 AM to 5/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Entrance ramp from WB I-290 52.0 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
26th St to 0.5 miles north of Chicago Skwy (I-90) 54.1 to 58.3 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation
63rd St to Wentworth Ave 58.7 to 58.9 Medium Left lane and left shoulder closed, one to three lanes open 3/31/15 12:00 AM to 8/31/15 11:59 PM IDOT Long Term Closure
at Wentworth Ave 58.9 Minor Right shoulder closed, all lanes open 3/20/15 12:00 AM to 6/1/15 11:59 PM IDOT ***Long Term Closure***
87th St to 91st St 61.8 to 62.3 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Dan Ryan Expy (I-94) / I-57 to SB Stony Island Feeder Entrance 62.9 to 65.6 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 11:59 AM IDOT Moving Operation
SB Stony Island Feeder Entrance to I-80 65.6 to 74.4 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 8:30 AM to 12:30 PM IDOT Moving Operation
0.5 miles north of Dolton Rd to 0.5 miles south of Dolton Rd 70.0 to 71.0 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Bishop Ford Fwy (IL-394) to IN State Line Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 2:00 PM IDOT Moving Operation

I-94 Express EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
26th St to 69th St 54.1 to 59.5 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation

I-94 Express WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
69th St to 26th St 59.5 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation

I-94 WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
IN State Line to Bishop Ford Fwy (IL-394) Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:30 AM to 2:30 PM IDOT Moving Operation
I-80 to NB Stony Island Feeder Exit 74.5 to 65.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 2:00 PM IDOT Moving Operation
NB Stony Island Feeder Exit to Dan Ryan Expy (I-94) / I-57 65.7 to 62.9 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:30 AM to 1:00 PM IDOT Moving Operation
Marquette Rd (67th St) to 63rd St 59.3 to 58.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
63rd St to 57th St 58.7 to 58.0 Medium Right lane and right shoulder closed, two lanes open 4/1/15 10:00 AM to 2:00 PM IDOT
Garfield Blvd (55th St) to 26th St 57.7 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
26th St to Stevenson Expy (I-55) 54.1 to 53.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Stevenson Expy (I-55) to Eisenhower Expy (I-290) 53.7 to 51.7 Medium Right lane and right shoulder closed, two to four lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from NB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from SB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to WB I-290 52.4 Minor Both shoulders closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT Reduced width ***Long Term Closure***
Exit ramp to EB I-290 52.4 Major All lanes and shoulders closed 3/13/15 12:00 AM to 12/31/16 11:59 PM IDOT ***Long Term Closure***
Roosevelt Rd to Eisenhower Expy (I-290) 52.2 to 51.7 Minor Both shoulders closed, all lanes open 3/13/15 12:00 AM to 6/1/16 11:59 PM IDOT Lanes shifted. 4 lanes total through section. ***Long Term Closure***
Entrance ramp from Roosevelt Rd 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from Taylor St 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Eisenhower Expy (I-290) to Jackson Blvd 51.7 to 51.5 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to I-190 51.7 to 79.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Grand Ave to Ohio Feeder 50.5 to 50.4 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Kennedy Junction to Park Ave West 43.5 to 23.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB IL-132 8.8 Minor Partial closure 3/20/15 7:00 AM to 5/1/15 11:59 PM Illinois Tollway Rdwy Reconst. and Plaza Repairs;Left Side of Ramp Closed; *** Long Term Closure ***
Entrance ramp from EB IL-132 8.6 Major All lanes and shoulders closed 2/27/15 7:00 AM to 5/19/15 11:59 PM Illinois Tollway Entrance Ramp Closed; *** Long Term Closure ***
Entrance ramp from WB IL-132 8.8 Minor Partial closure 3/11/15 6:00 AM to 4/17/15 11:59 PM Illinois Tollway Right Side of Ramp Closed; *** Long Term Closure ***

I-190 EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Entrance ramp from SB Mannheim Rd 1.3 Major All lanes and shoulders closed 3/18/15 12:00 AM to 7/17/15 11:59 PM IDOT Detour posted ***Long Term Closure***
Exit ramp to NB Mannheim Rd 1.4 Major All lanes and shoulders closed 3/9/15 12:00 AM to 7/17/15 11:59 PM IDOT DETOUR: NB Bessie Coleman to Zemke Blvd ***Long Term Closure***

I-190 WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Exit ramp to EB Mannheim Rd 77.4 Major All lanes and shoulders closed 3/16/15 12:00 AM to 9/4/15 11:59 PM IDOT Detour posted ***Long Term Closure***

I-290 EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Lake Cook Rd to Jane Addams Twy (I-90) Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Jane Addams Twy (I-90) to Wells St 0.0 to 30.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Entrance ramp from WB I-90 0.9 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
IL-53 to I-290 / IL-53 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Entrance ramp from SB I-294 15.5 Minor Left lane closed, up to one lanes open 4/1/15 9:00 AM to 12:01 PM Illinois Tollway Pavement, Drainage, Guardrail and Structural Repairs
Morgan St to Halsted St 29.5 to 29.8 Minor Both shoulders closed, all lanes open 2/10/15 12:00 AM to 6/1/15 11:59 PM IDOT Narrow Lanes, Weave traffic to right. Lane assignments: Congress (2 lanes), NB I-90/94 (1 Lane), SB I-90/94 (1 Lane). ***Long Term Closure***
Exit ramp to WB I-90/94 29.7 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 5/1/15 11:59 PM IDOT 11 ' Width ***Long Term Closure***
Exit ramp to EB I-90/94 29.7 Minor Right lane and both shoulders closed, up to two lanes open 6/22/14 12:00 AM to 5/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Halsted St to Canal St 29.8 to 30.2 Minor Both shoulders closed, all lanes open 6/21/14 12:00 AM to 6/1/15 11:59 PM IDOT Narrow Lanes ***Long Term Closure***
Entrance ramp from NB Dan Ryan Elevated 30.0 Minor Both shoulders closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT Reduced width ***Long Term Closure***
Entrance ramp from NB Dan Ryan Elevated 30.0 Major All lanes and shoulders closed 3/13/15 12:00 AM to 12/31/16 11:59 PM IDOT ***Long Term Closure***

I-290 WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Wells St to Jane Addams Twy (I-90) 30.5 to 0.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Canal St to Peoria St 30.2 to 29.7 Medium Left lane and both shoulders closed, two or three lanes shifted 12/1/14 12:00 AM to 12/1/15 11:59 PM IDOT Weave traffic Left to Right ***Long Term Closure***
Exit ramp to EB I-90 30.0 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Entrance ramp from EB Kennedy Local 29.7 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Exit ramp to Morgan St 29.7 Medium All lanes and shoulders closed 12/1/14 12:00 AM to 12/1/15 11:59 PM IDOT ***Long Term Closure***
Exit ramp to Thorndale Ave 5.5 Minor Partial closure 3/31/14 7:00 AM to 4/1/15 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from EB Thorndale Ave 5.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Entrance ramp from WB Thorndale Ave 4.8 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
I-290 / IL-53 to IL-53 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Jane Addams Twy (I-90) to Lake Cook Rd Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation

I-294 NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
at O'Hare Plaza 40.5 to 40.6 Medium Various lanes closed 4/1/15 9:00 AM to 3:30 PM Illinois Tollway Rdwy Reconst and Plaza Repairs; Moving Operation

I-294 SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Ballard Rd (+0.1 miles) to Oakton St (+0.2 miles) 44.5 to 43.0 Medium Right lane closed, three lanes open 4/1/15 10:00 AM to 1:00 PM Illinois Tollway
at O'Hare Plaza 40.3 to 40.2 Medium Various lanes closed 4/1/15 9:00 AM to 3:30 PM Illinois Tollway Rdwy Reconst and Plaza Repairs; Moving Operation
Exit ramp to SEB I-290 32.0 Minor Left lane closed, up to one lanes open 4/1/15 9:00 AM to 12:01 PM Illinois Tollway Pavement, Drainage, Guardrail and Structural Repairs
US-34 (+0.5 miles) to 55th St (+0.4 miles) 27.0 to 25.0 Medium Right lane closed, three lanes open 4/1/15 10:00 AM to 1:00 PM Illinois Tollway Moving Operation

US-41 NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Kennedy Junction to Park Ave West 43.5 to 23.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation

US-41 SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Park Ave West to Kennedy Junction 23.1 to 43.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation

IL-53 NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Wells St to Jane Addams Twy (I-90) 30.5 to 0.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Jane Addams Twy (I-90) to Lake Cook Rd Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
I-290 / IL-53 to IL-53 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Entrance ramp from EB I-90-Local 0.9 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from WB I-90-Local Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure

IL-53 SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Lake Cook Rd to Jane Addams Twy (I-90) Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Jane Addams Twy (I-90) to Wells St 0.0 to 30.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Entrance ramp from WB I-90 0.9 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
IL-53 to I-290 / IL-53 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation

IL-390 (Elgin O'Hare) EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
N Roselle Rd to Plum Grove Rd 9.5 to 10.5 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT

IL-390 (Elgin O'Hare) WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Entrance ramp from Springinsguth Rd 7.9 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT

IL-394 NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Sauk Trail to I-80 80.8 to 74.5 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation

IL-394 SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
SB Stony Island Feeder Entrance to I-80 65.6 to 74.4 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 8:30 AM to 12:30 PM IDOT Moving Operation
I-80 to Sauk Trail 74.4 to 80.8 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 8:30 AM to 2:00 PM IDOT Moving Operation

Bishop Ford NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Sauk Trail to I-80 80.8 to 74.5 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
I-80 to NB Stony Island Feeder Exit 74.5 to 65.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 2:00 PM IDOT Moving Operation
NB Stony Island Feeder Exit to Dan Ryan Expy (I-94) / I-57 65.7 to 62.9 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:30 AM to 1:00 PM IDOT Moving Operation

Bishop Ford SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Dan Ryan Expy (I-94) / I-57 to SB Stony Island Feeder Entrance 62.9 to 65.6 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 11:59 AM IDOT Moving Operation
SB Stony Island Feeder Entrance to I-80 65.6 to 74.4 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 8:30 AM to 12:30 PM IDOT Moving Operation
0.5 miles north of Dolton Rd to 0.5 miles south of Dolton Rd 70.0 to 71.0 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
I-80 to Sauk Trail 74.4 to 80.8 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 8:30 AM to 2:00 PM IDOT Moving Operation

Chicago Skyway EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Ramp from SB Dan Ryan Local to SB Chicago Skwy 58.8 to 59.3 Medium Left lane and left shoulder closed, one lane open 3/31/15 12:00 AM to 8/31/15 11:59 PM IDOT Long Term Closure

Dan Ryan Express NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
69th St to 26th St 59.5 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation

Dan Ryan Express SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
26th St to 69th St 54.1 to 59.5 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation

Dan Ryan Local NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Marquette Rd (67th St) to 63rd St 59.3 to 58.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
63rd St to 57th St 58.7 to 58.0 Medium Right lane and right shoulder closed, two lanes open 4/1/15 10:00 AM to 2:00 PM IDOT
Garfield Blvd (55th St) to 26th St 57.7 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
26th St to Stevenson Expy (I-55) 54.1 to 53.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Stevenson Expy (I-55) to Eisenhower Expy (I-290) 53.7 to 51.7 Medium Right lane and right shoulder closed, two to four lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from NB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from SB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to WB I-290 52.4 Minor Both shoulders closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT Reduced width ***Long Term Closure***
Exit ramp to EB I-290 52.4 Major All lanes and shoulders closed 3/13/15 12:00 AM to 12/31/16 11:59 PM IDOT ***Long Term Closure***
Roosevelt Rd to Eisenhower Expy (I-290) 52.2 to 51.7 Minor Both shoulders closed, all lanes open 3/13/15 12:00 AM to 6/1/16 11:59 PM IDOT Lanes shifted. 4 lanes total through section. ***Long Term Closure***
Entrance ramp from Roosevelt Rd 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from Taylor St 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***

Dan Ryan Local SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Eisenhower Expy (I-290) to Harrison St 51.6 to 51.7 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to 26th St 51.6 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Entrance ramp from EB Eisenhower / I-290 52.0 Minor Right lane and both shoulders closed, up to two lanes open 6/22/14 12:00 AM to 5/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Entrance ramp from WB I-290 52.0 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
26th St to 0.5 miles north of Chicago Skwy (I-90) 54.1 to 58.3 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation
63rd St to Wentworth Ave 58.7 to 58.9 Medium Left lane and left shoulder closed, one to three lanes open 3/31/15 12:00 AM to 8/31/15 11:59 PM IDOT Long Term Closure
at Wentworth Ave 58.9 Minor Right shoulder closed, all lanes open 3/20/15 12:00 AM to 6/1/15 11:59 PM IDOT ***Long Term Closure***
87th St to 91st St 61.8 to 62.3 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT

Edens NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Kennedy Junction to Park Ave West 43.5 to 23.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation

Edens SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Park Ave West to Kennedy Junction 23.1 to 43.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB Peterson Ave 41.3 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT

Edens Spur EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Park Ave West to Kennedy Junction 23.1 to 43.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation

Edens Spur WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Kennedy Junction to Park Ave West 43.5 to 23.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation

Eisenhower EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Jane Addams Twy (I-90) to Wells St 0.0 to 30.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Entrance ramp from SB I-294 15.5 Minor Left lane closed, up to one lanes open 4/1/15 9:00 AM to 12:01 PM Illinois Tollway Pavement, Drainage, Guardrail and Structural Repairs
Morgan St to Halsted St 29.5 to 29.8 Minor Both shoulders closed, all lanes open 2/10/15 12:00 AM to 6/1/15 11:59 PM IDOT Narrow Lanes, Weave traffic to right. Lane assignments: Congress (2 lanes), NB I-90/94 (1 Lane), SB I-90/94 (1 Lane). ***Long Term Closure***
Exit ramp to WB I-90/94 29.7 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 5/1/15 11:59 PM IDOT 11 ' Width ***Long Term Closure***
Exit ramp to EB I-90/94 29.7 Minor Right lane and both shoulders closed, up to two lanes open 6/22/14 12:00 AM to 5/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Halsted St to Canal St 29.8 to 30.2 Minor Both shoulders closed, all lanes open 6/21/14 12:00 AM to 6/1/15 11:59 PM IDOT Narrow Lanes ***Long Term Closure***
Entrance ramp from NB Dan Ryan Elevated 30.0 Minor Both shoulders closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT Reduced width ***Long Term Closure***
Entrance ramp from NB Dan Ryan Elevated 30.0 Major All lanes and shoulders closed 3/13/15 12:00 AM to 12/31/16 11:59 PM IDOT ***Long Term Closure***

Eisenhower WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Wells St to Jane Addams Twy (I-90) 30.5 to 0.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Canal St to Peoria St 30.2 to 29.7 Medium Left lane and both shoulders closed, two or three lanes shifted 12/1/14 12:00 AM to 12/1/15 11:59 PM IDOT Weave traffic Left to Right ***Long Term Closure***
Exit ramp to EB I-90 30.0 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Entrance ramp from EB Kennedy Local 29.7 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Exit ramp to Morgan St 29.7 Medium All lanes and shoulders closed 12/1/14 12:00 AM to 12/1/15 11:59 PM IDOT ***Long Term Closure***

Jane Addams Memorial (Northwest) EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Bartlett Rd to IL-72 (+0.3 miles) 60.4 to 61.7 Medium Right lane closed, two lanes open 4/1/15 9:00 AM to 7:00 PM Illinois Tollway Rdwy/Bridge Widening and Reconst
Entrance ramp from SB IL-53 Local 67.6 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from NB IL-53 Local 68.8 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from NB Elmhurst Rd 73.8 Medium All lanes and shoulders closed 9/8/14 12:00 AM to 6/30/15 12:00 AM Illinois Tollway Bridge Construction; ***Long Term Closure***

Jane Addams Memorial (Northwest) WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Exit ramp to NB Elmhurst Rd 73.8 Medium All lanes and shoulders closed 9/8/14 12:00 AM to 6/30/15 12:00 AM Illinois Tollway Bridge Construction; ***Long Term Closure***
Entrance ramp from SB Arlington Heights Rd 70.2 Minor Various lanes closed 3/23/15 7:00 AM to 11/20/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst;Right IPO Lane Closed; Right Side of Ramp Closed; ***Long Term Closure***
I-290 (-0.3 miles) to Meacham Rd (-0.1 miles) 68.5 to 67.5 Medium Left lane closed, two or three lanes open 3/17/15 7:00 AM to 8/1/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst; (Left lane of CD road to IL-290 / IL-53 closed); *** Long Term Closure ***
Ramp from WB I-90 to SB I-290/IL-53 68.3 to 68.2 Medium Left lane closed, two lanes open 3/31/15 7:00 AM to 4/14/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst; *** Long Term Closure ***
Entrance ramp from SB IL-53 Local 67.6 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from NB IL-53 Local 68.8 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Exit ramp to Roselle Rd 66.0 Minor Partial closure 6/17/14 5:00 AM to 6/6/15 11:59 PM Illinois Tollway ***Long Term Closure***; Right IPO Lane Closed

Kennedy Local EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Entrance ramp from SB Mannheim Rd 1.3 Major All lanes and shoulders closed 3/18/15 12:00 AM to 7/17/15 11:59 PM IDOT Detour posted ***Long Term Closure***
Exit ramp to NB Mannheim Rd 1.4 Major All lanes and shoulders closed 3/9/15 12:00 AM to 7/17/15 11:59 PM IDOT DETOUR: NB Bessie Coleman to Zemke Blvd ***Long Term Closure***
Ramp from EB I-90 to Cumberland Ave / IL-171 79.3 Minor Partial closure 11/25/14 7:00 AM to 4/30/15 11:59 PM IDOT ***Long Term Closure***
at Cumberland Ave (IL-171) 79.6 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
0.5 miles east of East River Rd to Eisenhower Expy (I-290) 79.6 to 51.6 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Ohio Feeder to Grand Ave 50.3 to 50.5 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Entrance ramp from WB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to WB I-290 51.4 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Jackson Blvd to Eisenhower Expy (I-290) 51.5 to 51.6 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to Harrison St 51.6 to 51.7 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to 26th St 51.6 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation

Kennedy Local WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Eisenhower Expy (I-290) to Jackson Blvd 51.7 to 51.5 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to I-190 51.7 to 79.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Grand Ave to Ohio Feeder 50.5 to 50.4 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to EB Mannheim Rd 77.4 Major All lanes and shoulders closed 3/16/15 12:00 AM to 9/4/15 11:59 PM IDOT Detour posted ***Long Term Closure***

Kingery EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Bishop Ford Fwy (IL-394) to IN State Line Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 2:00 PM IDOT Moving Operation

Kingery WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
IN State Line to Bishop Ford Fwy (IL-394) Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:30 AM to 2:30 PM IDOT Moving Operation

Reagan Memorial EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
US-30 (Rock Falls) to US-52 (Chicago Ave) (+0.2 miles) 44.2 to 55.2 Medium Various lanes closed 4/1/15 8:00 AM to 2:00 PM Illinois Tollway
IL-23 (4th St) to IL-23 (4th St) (+0.8 miles) 92.5 to 93.3 Medium Left lane closed, one lane open 4/1/15 8:00 AM to 6:00 PM Illinois Tollway Utility Work

Reagan Memorial WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Exit ramp to IL-59 123.7 Minor Partial closure 12/16/14 7:00 AM to 6/1/15 11:59 PM Illinois Tollway Right Side Ramp closed; ***Long Term Closure***
Peace Rd (+0.7 miles) to IL-23 (4th St) 93.3 to 92.5 Medium Left lane closed, one lane open 4/1/15 8:00 AM to 6:00 PM Illinois Tollway Utility Work
Burkett Rd (+0.8 miles) to US-30 (+0.2 miles) 55.2 to 44.0 Medium Various lanes closed 4/1/15 8:00 AM to 2:00 PM Illinois Tollway

Stevenson NB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Reed Rd to Lake Shore Dr (US-41) 233.5 to 293.7 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to SB IL-171 282.1 Minor All lanes and shoulders closed 3/30/15 7:00 AM to 10/31/15 11:59 PM IDOT ***Long Term Closure***
Exit ramp to NB Dan Ryan Expy 291.5 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***

Stevenson SB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Lake Shore Drive to Reed Rd 293.9 to 233.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to NB Dan Ryan Expy 292.9 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to SB IL-171 282.8 Major All lanes and shoulders closed 3/30/15 12:00 AM to 10/31/15 11:59 PM IDOT Long Term Closure
0.5 miles north of County Line Rd to 0.5 miles south of County Line Rd 276.9 to 275.9 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT

Tri-State NB/WB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
at O'Hare Plaza 40.5 to 40.6 Medium Various lanes closed 4/1/15 9:00 AM to 3:30 PM Illinois Tollway Rdwy Reconst and Plaza Repairs; Moving Operation
Exit ramp to EB IL-132 8.8 Minor Partial closure 3/20/15 7:00 AM to 5/1/15 11:59 PM Illinois Tollway Rdwy Reconst. and Plaza Repairs;Left Side of Ramp Closed; *** Long Term Closure ***
Entrance ramp from EB IL-132 8.6 Major All lanes and shoulders closed 2/27/15 7:00 AM to 5/19/15 11:59 PM Illinois Tollway Entrance Ramp Closed; *** Long Term Closure ***
Entrance ramp from WB IL-132 8.8 Minor Partial closure 3/11/15 6:00 AM to 4/17/15 11:59 PM Illinois Tollway Right Side of Ramp Closed; *** Long Term Closure ***

Tri-State SB/EB (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
Entrance ramp from WB IL-132 8.3 Minor Right lane closed, one lane open 3/9/15 12:00 AM to 5/1/15 12:00 AM Illinois Tollway Rdwy Reconst. and Plaza Repairs; Right Side Ramp closed; ***Long Term Closure***
Entrance ramp from EB IL-132 8.1 Minor Partial closure 3/6/15 7:00 AM to 5/1/15 11:59 PM Illinois Tollway Right Side of Ramp Closed; ***Long Term Closure***
Ballard Rd (+0.1 miles) to Oakton St (+0.2 miles) 44.5 to 43.0 Medium Right lane closed, three lanes open 4/1/15 10:00 AM to 1:00 PM Illinois Tollway
at O'Hare Plaza 40.3 to 40.2 Medium Various lanes closed 4/1/15 9:00 AM to 3:30 PM Illinois Tollway Rdwy Reconst and Plaza Repairs; Moving Operation
Exit ramp to SEB I-290 32.0 Minor Left lane closed, up to one lanes open 4/1/15 9:00 AM to 12:01 PM Illinois Tollway Pavement, Drainage, Guardrail and Structural Repairs
US-34 (+0.5 miles) to 55th St (+0.4 miles) 27.0 to 25.0 Medium Right lane closed, three lanes open 4/1/15 10:00 AM to 1:00 PM Illinois Tollway Moving Operation

Cook County (City of Chicago) (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB 130th St from Calumet River Bridge to Saginaw Ave Minor Various lanes closed 2/27/15 2:30 PM to 5/1/15 7:00 PM Chicago DOT 1 lane to be maintained in each direction
WB 130th St from Saginaw Ave to Calumet River Bridge Minor Various lanes closed 2/27/15 2:30 PM to 5/1/15 7:00 PM Chicago DOT 1 lane to be maintained in each direction
WB 18th St from Wentworth Ave (+0.1 miles) to Lumber St Medium All lanes and shoulders closed 12/6/14 7:00 PM to 4/1/15 7:00 PM Chicago DOT Detour EB 18th street traffic to SB Canal St, to EB Cermak Rd, to NB Archer Ave, to NB Clark St, and back to EB 18th St. Reverse for WB 18th St.
EB 35th St at Aberdeen St Medium All lanes and shoulders open 3/2/15 9:00 AM to 4/17/15 11:59 PM Chicago DOT Bridgeport Sewer Project::: Morgan Street will be detoured to Halsted Street via 31st and 35th Streets, while WB 35th Street will be detoured to Pershing via Racine and Halsted. Eastbound 35th Street traffic will be maintained at all times, as will local access.
WB 35th St at Aberdeen St Medium All lanes and shoulders open 3/2/15 9:00 AM to 4/17/15 11:59 PM Chicago DOT Bridgeport Sewer Project::: Morgan Street will be detoured to Halsted Street via 31st and 35th Streets, while WB 35th Street will be detoured to Pershing via Racine and Halsted. Eastbound 35th Street traffic will be maintained at all times, as will local access.
EB 63rd St at State St None All lanes and shoulders open 1/12/15 7:00 AM to 11/30/15 11:59 PM Chicago DOT Reconstruction of the 63rd Street Bridge over the Dan Ryan:: Detours are as follows: *Westbound 63rd Street traffic will be detoured to NB Wentworth, to WB 59th Street, to SB Yale, and back to WB 63rd Street. Additional wayfinding signage will be posted for the use of Halsted Street. *Eastbound 63rd Street traffic will be detoured to SB Halsted, to EB Marquette (67th Street), to NB State Street, and back to EB 63rd Street. *Vehicles exiting the Dan Ryan at 63rd Street, heading Eastbound, will be detoured to SB Wells/Wentworth, to EB Marquette, to NB State Street, and back to EB 63rd Street. Vehicles exiting the Dan Ryan and traveling Westbound will be unaffected. *Trucks will be redirected to 71st Street via State and Halsted Streets.
WB 63rd St at State St None All lanes and shoulders open 1/12/15 7:00 AM to 11/30/15 11:59 PM Chicago DOT Reconstruction of the 63rd Street Bridge over the Dan Ryan:: Detours are as follows: *Westbound 63rd Street traffic will be detoured to NB Wentworth, to WB 59th Street, to SB Yale, and back to WB 63rd Street. Additional wayfinding signage will be posted for the use of Halsted Street. *Eastbound 63rd Street traffic will be detoured to SB Halsted, to EB Marquette (67th Street), to NB State Street, and back to EB 63rd Street. *Vehicles exiting the Dan Ryan at 63rd Street, heading Eastbound, will be detoured to SB Wells/Wentworth, to EB Marquette, to NB State Street, and back to EB 63rd Street. Vehicles exiting the Dan Ryan and traveling Westbound will be unaffected. *Trucks will be redirected to 71st Street via State and Halsted Streets.
SB Ashland Ave from 36th St to 41st St Minor Various lanes closed 2/27/15 2:30 PM to 5/31/15 7:00 AM Chicago DOT Reconstruction
NB Damen Ave at 18th St Medium All lanes and shoulders closed 3/2/15 9:00 AM to 4/17/15 4:00 PM Chicago DOT Ongoing Sewer Project:::Damen Avenue will be detoured to Western Avenue via Cermak and Roosevelt, while 18th Street will be detoured to Cermak Road via Ashland and Western Avenues. Local access will be maintained.
SB Damen Ave at 18th St Medium All lanes and shoulders closed 3/2/15 9:00 AM to 4/17/15 4:00 PM Chicago DOT Ongoing Sewer Project:::Damen Avenue will be detoured to Western Avenue via Cermak and Roosevelt, while 18th Street will be detoured to Cermak Road via Ashland and Western Avenues. Local access will be maintained.
SB Kedzie Ave at 48th Pl Medium All lanes and shoulders closed 7/2/14 1:45 PM to 12/31/15 11:59 PM Chicago DOT Viaduct Clearance Improvement Project; Detour SB Kedzie to EB 47th St, to SB California, to WB 51st St, and back to SB Kedzie. Reverse for NB Kedzie Ave
NB Morgan St from 33rd Pl to 32nd St Medium All lanes and shoulders open 3/2/15 9:00 AM to 4/17/15 11:59 PM Chicago DOT Bridgeport Sewer Project::: Morgan Street will be detoured to Halsted Street via 31st and 35th Streets, while WB 35th Street will be detoured to Pershing via Racine and Halsted. Eastbound 35th Street traffic will be maintained at all times, as will local access.
SB Morgan St from 32nd St to 33rd Pl Medium All lanes and shoulders closed 3/2/15 9:00 AM to 4/17/15 11:59 PM Chicago DOT Bridgeport Sewer Project::: Morgan Street will be detoured to Halsted Street via 31st and 35th Streets, while WB 35th Street will be detoured to Pershing via Racine and Halsted. Eastbound 35th Street traffic will be maintained at all times, as will local access.
EB Roosevelt Rd from State St to Columbus Dr Minor Various lanes closed 2/27/15 2:45 PM to 5/31/15 4:00 PM Chicago DOT Intermodal Improvements
NB Torrence Ave from 130th St to 126th St Medium All lanes and shoulders closed 2/27/15 2:45 PM to 7/4/15 7:00 PM Chicago DOT
SB Torrence Ave from 126th St to 130th St Medium All lanes and shoulders closed 2/27/15 2:45 PM to 7/4/15 7:00 PM Chicago DOT
SWB Wacker Dr from State St to Lasalle St Minor Right lane closed, two lanes open 2/27/15 2:30 PM to 5/22/15 3:00 PM Chicago DOT

Cook County (Suburban) (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
NWB US-12 from Lake Cook Rd to Wooded Ridge Dr (+0.1 miles) Medium Various lanes closed 10/2/14 8:00 AM to 6/15/15 5:00 PM IDOT Resurfacing; Traffic will be reduced to one lane in each direction with flaggers at various locations in the work zone. The anticipated completion date is June 15.
SEB US-12 from Ela Rd to Lake Cook Rd Medium Various lanes closed 10/2/14 8:00 AM to 6/15/15 5:00 PM IDOT Resurfacing; Traffic will be reduced to one lane in each direction with flaggers at various locations in the work zone. The anticipated completion date is June 15.
NB IL-1 from Union Ave to Joe Orr Rd Medium Various lanes closed 3/16/15 7:00 AM to 8/31/15 7:00 PM IDOT Resurfacing
SB IL-1 from Joe Orr Rd to Union Ave Medium Various lanes closed 3/16/15 7:00 AM to 8/31/15 7:00 PM IDOT Resurfacing
EB IL-58 from Potter Rd to Lincoln St Medium Various lanes closed 3/30/15 7:00 AM to 8/31/15 11:59 PM IDOT Pavement patching, roadway milling and resurfacing; ***Long Term Closure***
WB IL-58 from Lincoln St to Potter Rd Medium Various lanes closed 3/30/15 7:00 AM to 8/31/15 11:59 PM IDOT Pavement patching, roadway milling and resurfacing; ***Long Term Closure***
EB IL-64 from Lavergne Ave to Roy Ave Medium Various lanes closed 8/10/14 6:00 AM to 5/31/15 11:59 PM IDOT Resurfacing, sewer, and landscaping
WB IL-64 from Roy Ave to Lavergne Ave Medium Various lanes closed 8/10/14 6:00 AM to 5/31/15 11:59 PM IDOT Resurfacing, sewer, and landscaping
EB IL-68 from Il-59 (Hawthorne Rd) to Rand Rd (US-12) Medium Various lanes closed 3/30/15 7:00 AM to 7/31/15 5:00 PM IDOT Resurfacing; Traffic reduced to one lane. Watch for flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment.
NB IL-171 at Willow Springs Rd Medium Various lanes closed 8/10/14 6:00 AM to 6/30/15 11:59 PM IDOT
NB IL-171 at Ridgewood Rd Medium Various lanes closed 8/10/14 6:00 AM to 6/30/15 11:59 PM IDOT Traffic Signal Modernization
SB IL-171 at Ridgewood Rd Medium Various lanes closed 8/10/14 6:00 AM to 6/30/15 11:59 PM IDOT Traffic Signal Modernization
SB IL-171 at 47th St Medium Various lanes closed 3/2/15 7:00 AM to 10/31/15 7:00 PM IDOT Bridge Reconstruction
NB Barrington Rd from Schaumburg Rd to IL-72 Minor Various lanes closed 10/6/14 9:00 AM to 6/10/15 11:59 PM IDOT Resurfacing; flagging operation, reduce speed, allow extra time for travel.Work will be suspended during the winter.
SB Barrington Rd from IL-72 to Schaumburg Rd Minor Various lanes closed 10/6/14 9:00 AM to 6/10/15 11:59 PM IDOT Resurfacing; flagging operation, reduce speed, allow extra time for travel.Work will be suspended during the winter.
EB Wille Rd at Elmhurst Rd (+0.1 miles) Medium All lanes and shoulders closed 10/20/14 6:00 AM to 12/31/15 11:59 PM Illinois Tollway Reconstruct Pavement

DuPage County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB IL-19 at e/o York Rd Major All lanes and shoulders closed 3/23/15 1:00 AM to 7/24/15 11:59 PM IDOT Detour info: Eastbound IL 19 traffic will turn north on to York Rd./Elmhurst Rd., east on IL Rte 72 (Touhy Ave), east on to IL72 (Higgins Rd), south on US Rte. 12/45/Mannheim Rd. Westbound IL 19 traffic will turn north on to US Route 12/45/Mannheim Rd., west on IL72/Higgins Rd., west on IL 72/Touhy Ave, south on Elmhurst Rd./York Rd.
WB IL-19 at e/o York Rd Major All lanes and shoulders closed 3/23/15 1:00 AM to 7/24/15 11:59 PM IDOT Detour info: Eastbound IL 19 traffic will turn north on to York Rd./Elmhurst Rd., east on IL Rte 72 (Touhy Ave), east on to IL72 (Higgins Rd), south on US Rte. 12/45/Mannheim Rd. Westbound IL 19 traffic will turn north on to US Route 12/45/Mannheim Rd., west on IL72/Higgins Rd., west on IL 72/Touhy Ave, south on Elmhurst Rd./York Rd.
NB IL-59 from Aurora Rd to Diehl Rd Medium Various lanes closed 8/10/14 6:00 AM to 8/31/15 11:59 PM IDOT Traffic signals, reconstruction
NB IL-59 from Diehl Rd to Ferry Rd Medium Various lanes closed 12/8/14 7:00 AM to 9/30/15 11:59 PM IDOT Lane Reduction
SB IL-59 from Diehl Rd to Aurora Rd Medium Various lanes closed 8/10/14 6:00 AM to 8/31/15 11:59 PM IDOT Traffic signals, reconstruction
NB IL-83 from 3rd Ave to Mark St Medium Various lanes closed 8/10/14 6:00 AM to 5/31/15 11:59 PM IDOT Traffic signal modernization
NB Mittel Dr at s/oThorndale Ave Medium All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM daily until 4/3/15 Illinois Tollway Traffic traveling to and from Thorndale Avenue will be detoured via Wood Dale Road
SB Mittel Dr at s/oThorndale Ave Medium All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM daily until 4/3/15 Illinois Tollway Traffic traveling to and from Thorndale Avenue will be detoured via Wood Dale Road
NB Pleasant Hill Rd from Geneva Rd to St Charles Rd Minor Various lanes closed 8/10/14 6:00 AM to 5/31/15 11:59 PM IDOT Milling and resurfacing
SB Pleasant Hill Rd from St Charles Rd to Geneva Rd Minor Various lanes closed 8/10/14 6:00 AM to 5/31/15 11:59 PM IDOT Milling and resurfacing

Kane County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
IL-25/Stearns Rd at UP Railroad Tracks Minor Various lanes closed 3/30/15 9:00 PM to 4/3/15 5:00 AM Gateway Railroad Bridge Work; Flagging Operation; A posted detour will route vehicles around the project site using IL. Rte. 64, IL Rte. 25, Kirk Road, Dunham Road and East Middle Street.
NB IL-25 from Stearns Rd to Dunham Rd Major All lanes and shoulders closed 4/1/15 9:00 PM to 4/2/15 5:00 AM daily until 4/3/15 IDOT Watch for flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment. Detour Will Be Posted.
SB IL-25 from Dunham Rd to Stearns Rd Major All lanes and shoulders closed 4/1/15 9:00 PM to 4/2/15 5:00 AM daily until 4/3/15 IDOT Watch for flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment. Detour Will Be Posted.
EB IL-68 from IL-72 to Prairie Lake Rd Medium Various lanes closed 3/30/15 8:00 AM to 6/17/15 11:59 PM IDOT Traffic reduced to one lane. Watch for flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment.
WB IL-68 from Prairie Lake Rd to IL-72 Medium Various lanes closed 3/30/15 8:00 AM to 6/17/15 11:59 PM IDOT Traffic reduced to one lane. Watch for flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment.
NB Tyrrell Rd at I-90 Minor Various lanes closed 3/16/15 9:00 AM to 12/31/15 11:59 PM Illinois Tollway Tyrrell Road Bridge Work
SB Tyrrell Rd at I-90 Minor Various lanes closed 3/16/15 9:00 AM to 12/31/15 11:59 PM Illinois Tollway Tyrrell Road Bridge Work

Kendall County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
NB IL-47 from IL-71 to Kennedy Rd Minor All lanes and shoulders open 9/24/14 12:00 AM to 12/31/15 12:00 AM IDOT Expect delays with lane restrictions for milling and resurfacing. Vehicle width restricted to 9' 4".
SB IL-47 from Kennedy Rd to IL-71 Minor All lanes and shoulders open 9/24/14 12:00 AM to 12/31/15 12:00 AM IDOT Expect delays with lane restrictions for milling and resurfacing. Vehicle width restricted to 9' 4".

Lake County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
NWB US-12 from Lake Cook Rd to Wooded Ridge Dr (+0.1 miles) Medium Various lanes closed 10/2/14 8:00 AM to 6/15/15 5:00 PM IDOT Resurfacing; Traffic will be reduced to one lane in each direction with flaggers at various locations in the work zone. The anticipated completion date is June 15.
SEB US-12 from Ela Rd to Lake Cook Rd Medium Various lanes closed 10/2/14 8:00 AM to 6/15/15 5:00 PM IDOT Resurfacing; Traffic will be reduced to one lane in each direction with flaggers at various locations in the work zone. The anticipated completion date is June 15.
EB IL-132 at Milwaukee Ave Medium Various lanes closed 7/28/14 7:00 AM to 10/30/15 3:00 PM Lake County Replace and Rehab Bridge over the Des Plaines River
WB IL-132 at Milwaukee Ave Medium Various lanes closed 7/28/14 7:00 AM to 10/30/15 3:00 PM Lake County Replace and Rehab Bridge over the Des Plaines River
EB IL-134 from US-12 to CR-V61 Medium Various lanes closed 9/22/14 7:00 AM to 5/1/15 3:00 PM Lake County Pavement Resurfacing
WB IL-134 from CR-V61 to US-12 Medium Various lanes closed 9/22/14 7:00 AM to 5/1/15 3:00 PM Lake County Pavement Resurfacing
EB IL-176 from Brown St to IL-60 Minor Various lanes closed 3/30/15 7:00 AM to 8/15/15 3:00 PM Lake County Resurfacing
WB IL-176 from IL-60 to Brown St Minor Various lanes closed 3/30/15 7:00 AM to 8/15/15 3:00 PM Lake County Resurfacing
EB CR-20 from IL-83 to US-45 Major All lanes and shoulders closed 3/30/15 7:00 AM to 6/5/15 3:00 PM Lake County Peterson Road Widening
WB CR-20 from US-45 to IL-83 Major All lanes and shoulders closed 3/30/15 7:00 AM to 6/5/15 3:00 PM Lake County Peterson Road Widening
EB CR-45 from Lakeside Dr to Lake St Minor Various lanes closed 2/25/15 7:00 AM to 11/25/16 3:00 PM Lake County Reconstruct and widen and construct railroad underpass
WB CR-45 from Lake St to Lakeside Dr Minor Various lanes closed 2/25/15 7:00 AM to 11/25/16 3:00 PM Lake County Reconstruct and widen and construct railroad underpass
EB Peterson Rd from US-45 to Butterfield Rd Medium Various lanes closed 3/19/15 10:45 AM to 5/1/15 8:12 AM Lake County
NB CR-4 at Roberts Rd Major All lanes and shoulders closed 8/11/14 7:00 AM to 11/27/15 3:00 PM Lake County Replacing the existing signalized intersection with a multi-late roundabout
SB CR-4 at Roberts Rd Major All lanes and shoulders closed 8/11/14 7:00 AM to 11/27/15 3:00 PM Lake County Replacing the existing signalized intersection with a multi-late roundabout

Lee County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
NEB IL-2 from Everett St (IL-26) to River Rd Medium Various lanes closed 9/15/14 8:00 AM to 10/31/15 11:59 PM IDOT Traffic will be reduced to one lane and regulated by flaggers; Expect minor backups; Max Width - 13'-6" - Effective 09/15/2014 through 10/31/2014.
SWB IL-2 from River Rd to Everett St (IL-26) Medium Various lanes closed 9/15/14 8:00 AM to 10/31/15 11:59 PM IDOT Traffic will be reduced to one lane and regulated by flaggers; Expect minor backups; Max Width - 13'-6" - Effective 09/15/2014 through 10/31/2014.

McHenry County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
NB IL-31 from Trinity Dr to James R Rakow Rd Medium Various lanes closed 5/27/14 7:00 AM to 6/1/15 11:59 PM IDOT

Rock Island County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB IL-92 from Loud Thunder Rd to 115th St Medium Various lanes closed 3/9/15 6:00 AM to 7/1/15 11:59 PM IDOT Traffic will be reduced to one lane traffic during working hours by flaggers
EB IL-92 from Loud Thunder Rd to 115th St Medium Various lanes closed 3/9/15 7:00 AM to 8/15/15 7:00 PM IDOT Road improvements; Flagging Operation
EB IL-92 from 115th Ave to Loud Thunder Rd Medium Various lanes closed 3/31/14 7:00 AM to 7/1/15 11:59 PM IDOT
WB IL-92 from 115th St to Loud Thunder Rd Medium Various lanes closed 3/9/15 6:00 AM to 7/1/15 11:59 PM IDOT Traffic will be reduced to one lane traffic during working hours by flaggers
WB IL-92 from 115th St to Loud Thunder Rd Medium Various lanes closed 3/9/15 7:00 AM to 8/15/15 7:00 PM IDOT Road improvements; Flagging Operation
WB IL-92 from Loud Thunder Rd to 115th Ave Medium Various lanes closed 3/31/14 7:00 AM to 7/1/15 11:59 PM IDOT

Stephenson County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
WB IL-75 from Pecatonica River to Galena Ave Medium All lanes and shoulders closed 9/15/14 8:00 AM to 6/30/15 11:59 PM IDOT The Road will be closed to traffic; Follow marked detour:: Road Closed - No Permits - Effective 09/29/2014 through 12/15/2014
WB IL-75 from Galena Ave to Pecatonica River Medium All lanes and shoulders closed 9/15/14 8:00 AM to 6/30/15 11:59 PM IDOT The Road will be closed to traffic; Follow marked detour:: Road Closed - No Permits - Effective 09/29/2014 through 12/15/2014
WB IL-75 from Pecatonica River to Galena Ave Medium All lanes and shoulders closed 9/15/14 8:00 AM to 6/30/15 11:59 PM IDOT The Road will be closed to traffic; Follow marked detour:: Road Closed - No Permits - Effective 09/29/2014 through 12/15/2014
EB Pecatonica River from Galena Ave to IL-75 Medium All lanes and shoulders closed 9/15/14 8:00 AM to 6/30/15 11:59 PM IDOT The Road will be closed to traffic; Follow marked detour:: Road Closed - No Permits - Effective 09/29/2014 through 12/15/2014

Whiteside County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
NB IL-40 from I-88 to US-30 Medium All lanes and shoulders open 3/16/15 7:00 AM to 12/15/15 11:59 PM IDOT Traffic will be reduced to one lane in each direction and separated by barrier wall::12'-6" - Max Width - Effective 03/30/2015 through 12/15/2015
SB IL-40 from US-30 to I-88 Medium All lanes and shoulders open 3/16/15 7:00 AM to 12/15/15 11:59 PM IDOT Traffic will be reduced to one lane in each direction and separated by barrier wall::12'-6" - Max Width - Effective 03/30/2015 through 12/15/2015
NB IL-78 at over French Creek Medium Various lanes closed 3/23/15 6:00 AM to 10/30/15 11:59 PM IDOT Traffic will be reduced to one lane and regulated by temporary traffic signals::Max Width - 10'-06" - Effective April 2 through October 16, 2015
SB IL-78 at over French Creek Medium Various lanes closed 3/23/15 6:00 AM to 10/30/15 11:59 PM IDOT Traffic will be reduced to one lane and regulated by temporary traffic signals::Max Width - 10'-06" - Effective April 2 through October 16, 2015

Will County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB US-30 from Il-59 to I-55 None All lanes shifted 4/1/15 8:00 AM to 12/31/16 11:59 PM IDOT Road widening and improved drainage system; Watch for flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment. Project scheduled to end Summer 2017.
WB US-30 from I-55 to Il-59 None All lanes shifted 4/1/15 8:00 AM to 12/31/16 11:59 PM IDOT Road widening and improved drainage system; Watch for flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment. Project scheduled to end Summer 2017.
NB IL-1 from Union Ave to Joe Orr Rd Medium Various lanes closed 3/16/15 7:00 AM to 8/31/15 7:00 PM IDOT Resurfacing
SB IL-1 from Joe Orr Rd to Union Ave Medium Various lanes closed 3/16/15 7:00 AM to 8/31/15 7:00 PM IDOT Resurfacing
NB IL-53 at Kankakee River Medium Various lanes closed 3/15/15 8:00 AM to 9/1/15 5:00 PM IDOT Bridge Work; Traffic will be reduced to one lane, with alternating traffic directions controlled by temporary traffic signals. Watch for flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment.
SB IL-53 at Kankakee River Medium Various lanes closed 3/15/15 8:00 AM to 9/1/15 5:00 PM IDOT Bridge Work; Traffic will be reduced to one lane, with alternating traffic directions controlled by temporary traffic signals. Watch for flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment.
EB Blodgett Rd from Grant Creek to I-55 Medium All lanes and shoulders closed 3/18/15 7:01 AM to 9/30/15 7:00 PM IDOT Bridge Work; Detour will be posted directing Blodgett Rd traffic south on I-55 to Lorenzo Rd, west to Will Rd, north to Blodgett Rd and to the reverse route.
WB Blodgett Rd from I-55 to Grant Creek Medium All lanes and shoulders closed 3/18/15 7:01 AM to 9/30/15 7:00 PM IDOT Bridge Work; Detour will be posted directing Blodgett Rd traffic south on I-55 to Lorenzo Rd, west to Will Rd, north to Blodgett Rd and to the reverse route.
NWB Water St (IL-102) from Ryan St to IL-53 Medium Various lanes closed 4/1/15 7:00 AM to 5/3/15 11:59 PM IDOT Resurfacing; Lane reduction to a single lane for both directions. Motorist are urged to pay close attention to flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment.
SEB Water St (IL-102) from IL-53 to Ryan St Medium Various lanes closed 4/1/15 7:00 AM to 5/3/15 11:59 PM IDOT Resurfacing; Lane reduction to a single lane for both directions. Motorist are urged to pay close attention to flaggers and signs in the work zones, obey the posted speed limits and be on the alert for workers and equipment.

Winnebago County (Illinois)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB US-20 from IL-2 to IL-251 Medium Various lanes closed 3/1/15 7:00 AM to 11/24/15 11:59 PM IDOT Traffic will be head to head separated by barrier wall. Expect moderate delays during rush hour and weekends* NB IL 2 to EB US 20 will be closed. There is a temporary connection so that NB will use the SB IL 2 to EB US 20 ramp (without going under the structures).* The EB US 20 to NB IL 2 ramp is closed. They will use the EB US 20 to SB IL 2 ramp (with signals).* The WB US 20 to NB IL 2 ramp is closed. They will use the WB US 20 to SB IL 2 ramp (with signals).* 12'-6" - Max. Width - Effective 03/01/2015 through 11/24/2015* IL 2 northbound to US 20 eastbound Ramp Closed - Effective 03/01/2015 through 11/24/2015* US 20 eastbound to IL 2 northbound Ramp Closed - Effective 03/01/2015 through 11/24/2015* US 20 Westbound to IL 2 northbound Ramp Closed - Effective 03/01/2015 through 11/24/2015
EB US-20 from IL-2 to IL-251 Medium Various lanes closed 3/1/15 6:00 AM to 11/24/15 11:59 PM IDOT Traffic will be head to head separated by barrier wall. Expect moderate delays during rush hour and weekends NB IL-2 to EB US-20 will be closed. There is a temporary connection so that NB will use the SB IL-2 to EB US-20 ramp (without going under the structures). The EB US-20 to NB IL-2 ramp is closed. They will use the EB US-20 to SB IL-2 ramp (with signals).
WB US-20 from IL-251 to IL-2 Medium Various lanes closed 3/1/15 6:00 AM to 11/24/15 11:59 PM IDOT Traffic will be head to head separated by barrier wall. Expect moderate delays during rush hour and weekends NB IL-2 to EB US-20 will be closed. There is a temporary connection so that NB will use the SB IL-2 to EB US-20 ramp (without going under the structures). The EB US-20 to NB IL-2 ramp is closed. They will use the EB US-20 to SB IL-2 ramp (with signals).
WB US-20 from IL-251 to IL-2 Medium Various lanes closed 3/1/15 7:00 AM to 11/24/15 11:59 PM IDOT Traffic will be head to head separated by barrier wall. Expect moderate delays during rush hour and weekends* NB IL 2 to EB US 20 will be closed. There is a temporary connection so that NB will use the SB IL 2 to EB US 20 ramp (without going under the structures).* The EB US 20 to NB IL 2 ramp is closed. They will use the EB US 20 to SB IL 2 ramp (with signals).* The WB US 20 to NB IL 2 ramp is closed. They will use the WB US 20 to SB IL 2 ramp (with signals).* 12'-6" - Max. Width - Effective 03/01/2015 through 11/24/2015* IL 2 northbound to US 20 eastbound Ramp Closed - Effective 03/01/2015 through 11/24/2015* US 20 eastbound to IL 2 northbound Ramp Closed - Effective 03/01/2015 through 11/24/2015* US 20 Westbound to IL 2 northbound Ramp Closed - Effective 03/01/2015 through 11/24/2015
NEB IL-2 from US-20 to Clifton Ave Medium Various lanes closed 5/5/14 7:00 AM to 7/1/15 11:59 PM IDOT Traffic will be reduced to one lane in each direction until December 5th, 2014.
SWB IL-2 from Clifton Ave to US-20 Medium Various lanes closed 5/5/14 7:00 AM to 7/1/15 11:59 PM IDOT Traffic will be reduced to one lane in each direction until December 5th, 2014.
EB IL-173 from Alpine Rd to I-39/90 Medium Various lanes closed 3/17/14 7:00 AM to 11/6/15 11:59 PM IDOT 9'-6" - Max Width - Effective 03/17/2014 through 12/12/2014
WB IL-173 from I-39/90 to Alpine Rd Medium Various lanes closed 3/17/14 7:00 AM to 11/6/15 11:59 PM IDOT 9'-6" - Max Width - Effective 03/17/2014 through 12/12/2014
NB Mitchell Rd from IL-173 to Swanson Rd Medium All lanes and shoulders closed 3/16/15 9:00 AM to 6/30/15 11:59 PM IDOT
SB Mitchell Rd from Swanson Rd to IL-173 Medium All lanes and shoulders closed 3/16/15 9:00 AM to 6/30/15 11:59 PM IDOT

I-80 EB (Indiana)
Location Mile Marker Severity Closure Details Time Periods Source Description
Exit ramp to WB I-90 15.3 Major All lanes and shoulders closed 3/18/15 8:00 AM to 6/29/15 11:59 PM Indiana Toll Road Lake Station entrance ramp closed for Bridge Demo/Rebuild for 13 weeks ***Long Term Closure***
15th Ave (-0.1 miles) to I-94 (-0.3 miles) 17.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures - All EB lanes
Bittersweet Rd (+0.5 miles) to Ash Rd (-0.1 miles) 85.0 to 87.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Pothole Patching
250 (-0.2 miles) to 475 East (+0.5 miles) 123.0 to 126.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Crack Sealing
IN-327 (-0.5 miles) to 800 134.0 to 136.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Guardrail Repair

I-80 WB (Indiana)
Location Mile Marker Severity Closure Details Time Periods Source Description
Hamstrom Rd (+0.3 miles) to I-94 (+0.3 miles) 24.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures- All WB lanes
I-94 (+0.2 miles) to IN-51 (-0.4 miles) 21.1 to 20.8 Medium Right lane closed, one lane open 4/1/15 12:00 PM to 3:30 PM Indiana Toll Road Remove Temporary Barrier Wall / Install Barricades; Once barrier wall is removed, barricades will be moved into place for ramp closure
Exit ramp to I-94 21.0 Major All lanes and shoulders closed 3/18/15 7:00 AM to 4/5/15 11:59 PM Indiana Toll Road Lake Station exit ramp closed for Ramp Demo/Rebuild ***Long Term***

I-90 EB (Indiana)
Location Mile Marker Severity Closure Details Time Periods Source Description
at Knights Of Columbus Dr 6.5 Medium Left lane closed, one lane open 4/1/15 12:00 AM to 1:00 PM,
4/1/15 8:00 PM to 4/2/15 12:00 AM
Indiana Toll Road MOT Installation
15th Ave (-0.1 miles) to I-94 (-0.3 miles) 17.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures - All EB lanes
Bittersweet Rd (+0.5 miles) to Ash Rd (-0.1 miles) 85.0 to 87.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Pothole Patching
250 (-0.2 miles) to 475 East (+0.5 miles) 123.0 to 126.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Crack Sealing
IN-327 (-0.5 miles) to 800 134.0 to 136.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Guardrail Repair

I-90 WB (Indiana)
Location Mile Marker Severity Closure Details Time Periods Source Description
Hamstrom Rd (+0.3 miles) to I-94 (+0.3 miles) 24.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures- All WB lanes
I-94 (+0.2 miles) to IN-51 (-0.4 miles) 21.1 to 20.8 Medium Right lane closed, one lane open 4/1/15 12:00 PM to 3:30 PM Indiana Toll Road Remove Temporary Barrier Wall / Install Barricades; Once barrier wall is removed, barricades will be moved into place for ramp closure
Exit ramp to I-94 21.0 Major All lanes and shoulders closed 3/18/15 7:00 AM to 4/5/15 11:59 PM Indiana Toll Road Lake Station exit ramp closed for Ramp Demo/Rebuild ***Long Term***
Entrance ramp from I-80/I-94 20.4 Major All lanes and shoulders closed 3/18/15 8:00 AM to 6/29/15 11:59 PM Indiana Toll Road Lake Station entrance ramp closed for Bridge Demo/Rebuild for 13 weeks ***Long Term Closure***
at Knights Of Columbus Dr (+0.1 miles) 6.5 Medium Left lane closed, one lane open 4/1/15 8:00 PM to 4/2/15 12:00 AM Indiana Toll Road MOT Installation

I-94 WB (Indiana)
Location Mile Marker Severity Closure Details Time Periods Source Description
Entrance ramp from WB I-80 15.3 Major All lanes and shoulders closed 3/18/15 7:00 AM to 4/5/15 11:59 PM Indiana Toll Road Lake Station exit ramp closed for Ramp Demo/Rebuild ***Long Term***

Borman WB (Indiana)
Location Mile Marker Severity Closure Details Time Periods Source Description
Entrance ramp from WB I-80 15.3 Major All lanes and shoulders closed 3/18/15 7:00 AM to 4/5/15 11:59 PM Indiana Toll Road Lake Station exit ramp closed for Ramp Demo/Rebuild ***Long Term***

Indiana Toll Road (East-West) EB (Indiana)
Location Mile Marker Severity Closure Details Time Periods Source Description
at Knights Of Columbus Dr 6.5 Medium Left lane closed, one lane open 4/1/15 12:00 AM to 1:00 PM,
4/1/15 8:00 PM to 4/2/15 12:00 AM
Indiana Toll Road MOT Installation
15th Ave (-0.1 miles) to I-94 (-0.3 miles) 17.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures - All EB lanes
Bittersweet Rd (+0.5 miles) to Ash Rd (-0.1 miles) 85.0 to 87.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Pothole Patching
250 (-0.2 miles) to 475 East (+0.5 miles) 123.0 to 126.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Crack Sealing
IN-327 (-0.5 miles) to 800 134.0 to 136.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Guardrail Repair

Indiana Toll Road (East-West) WB (Indiana)
Location Mile Marker Severity Closure Details Time Periods Source Description
Hamstrom Rd (+0.3 miles) to I-94 (+0.3 miles) 24.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures- All WB lanes
I-94 (+0.2 miles) to IN-51 (-0.4 miles) 21.1 to 20.8 Medium Right lane closed, one lane open 4/1/15 12:00 PM to 3:30 PM Indiana Toll Road Remove Temporary Barrier Wall / Install Barricades; Once barrier wall is removed, barricades will be moved into place for ramp closure
Exit ramp to I-94 21.0 Major All lanes and shoulders closed 3/18/15 7:00 AM to 4/5/15 11:59 PM Indiana Toll Road Lake Station exit ramp closed for Ramp Demo/Rebuild ***Long Term***
Entrance ramp from I-80/I-94 20.4 Major All lanes and shoulders closed 3/18/15 8:00 AM to 6/29/15 11:59 PM Indiana Toll Road Lake Station entrance ramp closed for Bridge Demo/Rebuild for 13 weeks ***Long Term Closure***
at Knights Of Columbus Dr (+0.1 miles) 6.5 Medium Left lane closed, one lane open 4/1/15 8:00 PM to 4/2/15 12:00 AM Indiana Toll Road MOT Installation

I-94 EB (Michigan)
Location Mile Marker Severity Closure Details Time Periods Source Description
Exit ramp to SB Sprinkle Rd 79.2 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Exit ramp to SB Sprinkle Rd 79.2 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Entrance ramp from SB Sprinkle Rd 79.5 Medium All lanes and shoulders open 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Entrance ramp from NB Sprinkle Rd 79.8 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Entrance ramp from NB Sprinkle Rd 79.8 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
at Cork St 79.9 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Climax And Battle Creek Rd (-0.1 miles) to I-69 92.0 to 108.2 Medium Various lanes closed 3/20/15 1:00 PM to 11/28/15 1:00 PM MDOT

I-94 WB (Michigan)
Location Mile Marker Severity Closure Details Time Periods Source Description
I-69 to Climax And Battle Creek Rd (+0.1 miles) 108.2 to 92.0 Medium Various lanes closed 3/20/15 1:00 PM to 11/28/15 1:00 PM MDOT
Exit ramp to EB Cork St 80.0 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Exit ramp to Cork St 80.0 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
at Cork St 79.9 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Entrance ramp from NB Sprinkle Rd 79.7 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Entrance ramp from NB Sprinkle Rd 79.7 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Entrance ramp from SB Sprinkle Rd 79.4 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Entrance ramp from SB Sprinkle Rd 79.4 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information

I-196 NB (Michigan)
Location Mile Marker Severity Closure Details Time Periods Source Description
at M-43 18.6 Medium Various lanes closed 3/24/15 7:00 AM to 5/11/15 11:59 PM MDOT *** Long Term Closure ***

I-196 SB (Michigan)
Location Mile Marker Severity Closure Details Time Periods Source Description
at M-43 18.6 Medium Various lanes closed 3/24/15 7:00 AM to 5/11/15 11:59 PM MDOT *** Long Term Closure ***

Allegan County (Michigan)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB M-222 at US-131 Medium All lanes and shoulders closed 2/9/15 7:00 AM to 7/9/15 11:59 PM MDOT Bridge Replacement; Traffic will follow the posted detours on US-131 and M-89; Nightime Lane Closures on US-131.
WB M-222 at US-131 Medium All lanes and shoulders closed 2/9/15 7:00 AM to 7/9/15 11:59 PM MDOT Bridge Replacement; Traffic will follow the posted detours on US-131 and M-89; Nightime Lane Closures on US-131.

Berrien County (Michigan)
Location Mile Marker Severity Closure Details Time Periods Source Description
NB M-139 at Niles Main St Bridge Medium All lanes and shoulders closed 10/13/14 6:00 AM to 11/15/15 11:59 PM MDOT During construction, traffic will be detoured on Lincoln Avenue, Grant Street, Broadway Street, North 5th Street, M-51, and Wayne Street.
NWB M-139 from George Ave to US-31 Minor All lanes and shoulders open 3/25/15 7:00 AM to 7/31/15 11:59 PM MDOT Lane Shifts for Water and Sewer Installation
SB M-139 at Niles Main St Bridge Medium All lanes and shoulders closed 10/13/14 6:00 AM to 11/15/15 11:59 PM MDOT During construction, traffic will be detoured on Lincoln Avenue, Grant Street, Broadway Street, North 5th Street, M-51, and Wayne Street.
SEB M-139 from US-31 to George Ave Minor All lanes and shoulders open 3/25/15 7:00 AM to 7/31/15 11:59 PM MDOT Lane Shifts for Water and Sewer Installation

Kalamazoo County (Michigan)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB Cork St from I-94 to I-94 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
WB Cork St from I-94 to I-94 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
NB Sprinkle Rd from Vanrick Dr to Cork St Medium Various lanes closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
SB Sprinkle Rd from Cork St to Vanrick Dr Medium Various lanes closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information

St Joseph County (Michigan)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB M-60 from Mendon Pky to Congress St Medium Various lanes closed 3/23/15 7:00 AM to 8/7/15 11:59 PM MDOT Reconstruction will include drainage upgrades, concrete sidewalk construction, water main work and sign upgrades. Eastbound M-60 will be open through Mendon during construction. Westbound M-60 will be detoured on M-66 and M-86.
WB M-60 from Congress St to Mendon Pky Medium Various lanes closed 3/23/15 7:00 AM to 8/7/15 11:59 PM MDOT Reconstruction will include drainage upgrades, concrete sidewalk construction, water main work and sign upgrades. Eastbound M-60 will be open through Mendon during construction. Westbound M-60 will be detoured on M-66 and M-86.

I-39 NB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
CR-J (+0.1 miles) to Kent Rd 115.5 to 114.3 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

I-39 SB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
Black Rd (+0.4 miles) to CR-J (-0.2 miles) 113.9 to 115.5 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

I-80 EB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
Mississippi River to IL-84 0.0 to 0.3 Medium Various lanes closed 3/20/15 7:00 AM to 4/14/15 7:00 PM IDOT One direction at a time will be closed to all traffic for 4 days from Friday night at 8:00 PM until Tuesday. There will be a total of two closures, one in each direction. We will not close over the Easter weekend. --Westbound I-80 Rock Closed - No permits - Effective March 27 through March 31, 2015 --Westbound I-80 Rock Closed - No permits - Effective April 10 through April 14, 2015 --Eastbound I-80 Road Closed - No permits - Effective April 10 through April 14, 2015 --Eastbouhd I-80 Road Closed - No permits - Effective April 17 through April 21, 2015
Kendall County Line to Harlem Ave (IL-43) 122.6 to 148.8 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to NB Harlem Ave 148.9 Minor Partial closure 3/31/14 12:00 AM to 12/1/15 11:59 PM IDOT ***Long Term Closure***
Bishop Ford Fwy (IL-394) to IN State Line Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 2:00 PM IDOT Moving Operation
Exit ramp to WB I-90 15.3 Major All lanes and shoulders closed 3/18/15 8:00 AM to 6/29/15 11:59 PM Indiana Toll Road Lake Station entrance ramp closed for Bridge Demo/Rebuild for 13 weeks ***Long Term Closure***
15th Ave (-0.1 miles) to I-94 (-0.3 miles) 17.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures - All EB lanes
Bittersweet Rd (+0.5 miles) to Ash Rd (-0.1 miles) 85.0 to 87.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Pothole Patching
250 (-0.2 miles) to 475 East (+0.5 miles) 123.0 to 126.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Crack Sealing
IN-327 (-0.5 miles) to 800 134.0 to 136.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Guardrail Repair

I-80 WB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
Hamstrom Rd (+0.3 miles) to I-94 (+0.3 miles) 24.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures- All WB lanes
I-94 (+0.2 miles) to IN-51 (-0.4 miles) 21.1 to 20.8 Medium Right lane closed, one lane open 4/1/15 12:00 PM to 3:30 PM Indiana Toll Road Remove Temporary Barrier Wall / Install Barricades; Once barrier wall is removed, barricades will be moved into place for ramp closure
Exit ramp to I-94 21.0 Major All lanes and shoulders closed 3/18/15 7:00 AM to 4/5/15 11:59 PM Indiana Toll Road Lake Station exit ramp closed for Ramp Demo/Rebuild ***Long Term***
IN State Line to Bishop Ford Fwy (IL-394) Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:30 AM to 2:30 PM IDOT Moving Operation
Harlem Ave (IL-43) to Kendall County Line 148.8 to 122.6 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
IL-84 to Mississippi River 0.3 to 0.0 Medium Various lanes closed 3/20/15 7:00 AM to 4/14/15 7:00 PM IDOT One direction at a time will be closed to all traffic for 4 days from Friday night at 8:00 PM until Tuesday. There will be a total of two closures, one in each direction. We will not close over the Easter weekend. --Westbound I-80 Rock Closed - No permits - Effective March 27 through March 31, 2015 --Westbound I-80 Rock Closed - No permits - Effective April 10 through April 14, 2015 --Eastbound I-80 Road Closed - No permits - Effective April 10 through April 14, 2015 --Eastbouhd I-80 Road Closed - No permits - Effective April 17 through April 21, 2015

I-90 EB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
Black Rd (+0.4 miles) to CR-J (-0.2 miles) 113.9 to 115.5 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA
Bartlett Rd to IL-72 (+0.3 miles) 60.4 to 61.7 Medium Right lane closed, two lanes open 4/1/15 9:00 AM to 7:00 PM Illinois Tollway Rdwy/Bridge Widening and Reconst
Entrance ramp from SB IL-53 Local 67.6 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from NB IL-53 Local 68.8 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from NB Elmhurst Rd 73.8 Medium All lanes and shoulders closed 9/8/14 12:00 AM to 6/30/15 12:00 AM Illinois Tollway Bridge Construction; ***Long Term Closure***
Ramp from EB I-90 to Cumberland Ave / IL-171 79.3 Minor Partial closure 11/25/14 7:00 AM to 4/30/15 11:59 PM IDOT ***Long Term Closure***
at Cumberland Ave (IL-171) 79.6 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
0.5 miles east of East River Rd to Eisenhower Expy (I-290) 79.6 to 51.6 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Ohio Feeder to Grand Ave 50.3 to 50.5 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Entrance ramp from WB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to WB I-290 51.4 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Jackson Blvd to Eisenhower Expy (I-290) 51.5 to 51.6 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to Harrison St 51.6 to 51.7 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to 26th St 51.6 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Entrance ramp from EB Eisenhower / I-290 52.0 Minor Right lane and both shoulders closed, up to two lanes open 6/22/14 12:00 AM to 5/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Entrance ramp from WB I-290 52.0 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
26th St to 0.5 miles north of Chicago Skwy (I-90) 54.1 to 58.3 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation
63rd St to Wentworth Ave 58.7 to 58.9 Medium Left lane and left shoulder closed, one to three lanes open 3/31/15 12:00 AM to 8/31/15 11:59 PM IDOT Long Term Closure
Ramp from SB Dan Ryan Local to SB Chicago Skwy 58.8 to 59.3 Medium Left lane and left shoulder closed, one lane open 3/31/15 12:00 AM to 8/31/15 11:59 PM IDOT Long Term Closure
at Knights Of Columbus Dr 6.5 Medium Left lane closed, one lane open 4/1/15 12:00 AM to 1:00 PM,
4/1/15 8:00 PM to 4/2/15 12:00 AM
Indiana Toll Road MOT Installation
15th Ave (-0.1 miles) to I-94 (-0.3 miles) 17.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures - All EB lanes
Bittersweet Rd (+0.5 miles) to Ash Rd (-0.1 miles) 85.0 to 87.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Pothole Patching
250 (-0.2 miles) to 475 East (+0.5 miles) 123.0 to 126.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Crack Sealing
IN-327 (-0.5 miles) to 800 134.0 to 136.0 Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM Indiana Toll Road Guardrail Repair

I-90 Express EB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
26th St to 69th St 54.1 to 59.5 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation

I-90 Express WB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
69th St to 26th St 59.5 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation

I-90 WB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
Hamstrom Rd (+0.3 miles) to I-94 (+0.3 miles) 24.0 to 21.0 Major All lanes and shoulders closed 4/1/15 8:00 PM to 4/2/15 5:00 AM Indiana Toll Road Demo of BHX-A over I-90; 20 minute rolling closures- All WB lanes
I-94 (+0.2 miles) to IN-51 (-0.4 miles) 21.1 to 20.8 Medium Right lane closed, one lane open 4/1/15 12:00 PM to 3:30 PM Indiana Toll Road Remove Temporary Barrier Wall / Install Barricades; Once barrier wall is removed, barricades will be moved into place for ramp closure
Exit ramp to I-94 21.0 Major All lanes and shoulders closed 3/18/15 7:00 AM to 4/5/15 11:59 PM Indiana Toll Road Lake Station exit ramp closed for Ramp Demo/Rebuild ***Long Term***
Entrance ramp from I-80/I-94 20.4 Major All lanes and shoulders closed 3/18/15 8:00 AM to 6/29/15 11:59 PM Indiana Toll Road Lake Station entrance ramp closed for Bridge Demo/Rebuild for 13 weeks ***Long Term Closure***
at Knights Of Columbus Dr (+0.1 miles) 6.5 Medium Left lane closed, one lane open 4/1/15 8:00 PM to 4/2/15 12:00 AM Indiana Toll Road MOT Installation
Marquette Rd (67th St) to 63rd St 59.3 to 58.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
63rd St to 57th St 58.7 to 58.0 Medium Right lane and right shoulder closed, two lanes open 4/1/15 10:00 AM to 2:00 PM IDOT
Garfield Blvd (55th St) to 26th St 57.7 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
26th St to Stevenson Expy (I-55) 54.1 to 53.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Stevenson Expy (I-55) to Eisenhower Expy (I-290) 53.7 to 51.7 Medium Right lane and right shoulder closed, two to four lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from NB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from SB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to EB I-290 52.4 Major All lanes and shoulders closed 3/13/15 12:00 AM to 12/31/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to WB I-290 52.4 Minor Both shoulders closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT Reduced width ***Long Term Closure***
Roosevelt Rd to Eisenhower Expy (I-290) 52.2 to 51.7 Minor Both shoulders closed, all lanes open 3/13/15 12:00 AM to 6/1/16 11:59 PM IDOT Lanes shifted. 4 lanes total through section. ***Long Term Closure***
Entrance ramp from Roosevelt Rd 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from Taylor St 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Eisenhower Expy (I-290) to Jackson Blvd 51.7 to 51.5 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to I-190 51.7 to 79.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Grand Ave to Ohio Feeder 50.5 to 50.4 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to NB Elmhurst Rd 73.8 Medium All lanes and shoulders closed 9/8/14 12:00 AM to 6/30/15 12:00 AM Illinois Tollway Bridge Construction; ***Long Term Closure***
Entrance ramp from SB Arlington Heights Rd 70.2 Minor Various lanes closed 3/23/15 7:00 AM to 11/20/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst;Right IPO Lane Closed; Right Side of Ramp Closed; ***Long Term Closure***
I-290 (-0.3 miles) to Meacham Rd (-0.1 miles) 68.5 to 67.5 Medium Left lane closed, two or three lanes open 3/17/15 7:00 AM to 8/1/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst; (Left lane of CD road to IL-290 / IL-53 closed); *** Long Term Closure ***
Ramp from WB I-90 to SB I-290/IL-53 68.3 to 68.2 Medium Left lane closed, two lanes open 3/31/15 7:00 AM to 4/14/15 11:59 PM Illinois Tollway Rdwy Widening and Reconst; *** Long Term Closure ***
Entrance ramp from SB IL-53 Local 67.6 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Entrance ramp from NB IL-53 Local 68.8 Minor Both shoulders closed, all lanes open 3/2/15 12:00 AM to 11/20/15 11:59 PM IDOT Long Term Closure
Exit ramp to Roselle Rd 66.0 Minor Partial closure 6/17/14 5:00 AM to 6/6/15 11:59 PM Illinois Tollway ***Long Term Closure***; Right IPO Lane Closed
CR-J (+0.1 miles) to Kent Rd 115.5 to 114.3 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

I-94 EB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
Black Rd (+0.4 miles) to CR-J (-0.2 miles) 113.9 to 115.5 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA
WI-100 (-0.2 miles) to I-894 303.5 to 304.3 Major All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 5:00 AM WisDOT Construction - Detour: Take I-94 EB to HWY 100 to Greenfield to US 45 North to I-94 EB. OR Take I-94 EB to HWY 100 to Watertown Plank to US45 NB.
Canal St to National/WI-59 310.9 to 311.5 Minor Right shoulder closed, all lanes open 3/24/15 9:00 AM to 5/15/15 11:59 PM WisDOT Long term closure until mid May 2015; *** Long Term Closure ***
Ramp from SB I-43 to National Ave 311.3 Minor Left shoulder closed, all lanes open 3/24/15 9:00 AM to 5/15/15 11:59 PM WisDOT Long term closure until mid May 2015; *** Long Term Closure ***
at Lincoln Ave 313.0 Major Right two lanes closed, one lane open 3/31/15 9:30 PM to 4/1/15 5:30 PM WisDOT
Entrance ramp from SEB WI-100 323.1 Major All lanes and shoulders closed 3/23/15 12:00 AM to 5/22/15 11:45 PM WisDOT Construction - Detour: Take HWY 100 South to Greenfield to I-894/US45 North to 94 East. OR Take HWY 100 North to Watertown Plank to Glenview to I-94 East
50th Rd to 58th Rd 331.9 to 334.9 Medium Various lanes closed 3/20/15 12:00 AM to 11/25/15 11:45 PM WisDOT Construction - N-S FREEWAY, STH 20 INTERCHANGE | MAINLINE & RAMPS | I 94 | RACINE
Exit ramp to WB WI-20 332.7 Major All lanes and shoulders closed 3/20/15 12:00 AM to 7/2/15 11:45 PM WisDOT Construction - Detour: Use I-94 EB (SB) to County K to West Frontage Road to WIS 20; *** Long Term Closure ***
at WI-20 333.1 Medium Right lane closed, two lanes open 3/21/15 8:00 AM to 11/30/15 11:59 PM WisDOT *** Long Term Closure ***
Entrance ramp from EB WI-20 332.7 Major All lanes and shoulders closed 3/20/15 12:00 AM to 11/24/15 11:45 PM WisDOT Construction - Detour: Use WIS 20 to West Frontage Road to 58th Road to West Frontage Road to WIS 11 to I-94 EB (SB); *** Long Term Closure ***
Entrance ramp from WB IL-132 8.3 Minor Right lane closed, one lane open 3/9/15 12:00 AM to 5/1/15 12:00 AM Illinois Tollway Rdwy Reconst. and Plaza Repairs; Right Side Ramp closed; ***Long Term Closure***
Entrance ramp from EB IL-132 8.1 Minor Partial closure 3/6/15 7:00 AM to 5/1/15 11:59 PM Illinois Tollway Right Side of Ramp Closed; ***Long Term Closure***
Park Ave West to Kennedy Junction 23.1 to 43.5 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB Peterson Ave 41.3 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
0.5 miles east of East River Rd to Eisenhower Expy (I-290) 79.6 to 51.6 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Ohio Feeder to Grand Ave 50.3 to 50.5 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Entrance ramp from WB Ohio St 50.1 Minor Partial closure 4/1/15 9:00 AM to 3:00 PM IDOT
Exit ramp to WB I-290 51.4 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Jackson Blvd to Eisenhower Expy (I-290) 51.5 to 51.6 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to Harrison St 51.6 to 51.7 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to 26th St 51.6 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Entrance ramp from EB Eisenhower / I-290 52.0 Minor Right lane and both shoulders closed, up to two lanes open 6/22/14 12:00 AM to 5/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
Entrance ramp from WB I-290 52.0 Minor Both shoulders closed, all lanes open 6/1/14 12:00 AM to 12/1/15 11:59 PM IDOT 11' Width ***Long Term Closure***
26th St to 0.5 miles north of Chicago Skwy (I-90) 54.1 to 58.3 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation
63rd St to Wentworth Ave 58.7 to 58.9 Medium Left lane and left shoulder closed, one to three lanes open 3/31/15 12:00 AM to 8/31/15 11:59 PM IDOT Long Term Closure
at Wentworth Ave 58.9 Minor Right shoulder closed, all lanes open 3/20/15 12:00 AM to 6/1/15 11:59 PM IDOT ***Long Term Closure***
87th St to 91st St 61.8 to 62.3 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Dan Ryan Expy (I-94) / I-57 to SB Stony Island Feeder Entrance 62.9 to 65.6 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 11:59 AM IDOT Moving Operation
SB Stony Island Feeder Entrance to I-80 65.6 to 74.4 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 8:30 AM to 12:30 PM IDOT Moving Operation
0.5 miles north of Dolton Rd to 0.5 miles south of Dolton Rd 70.0 to 71.0 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Bishop Ford Fwy (IL-394) to IN State Line Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 2:00 PM IDOT Moving Operation
Exit ramp to SB Sprinkle Rd 79.2 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Exit ramp to SB Sprinkle Rd 79.2 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Entrance ramp from SB Sprinkle Rd 79.5 Medium All lanes and shoulders open 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Entrance ramp from NB Sprinkle Rd 79.8 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Entrance ramp from NB Sprinkle Rd 79.8 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
at Cork St 79.9 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Climax And Battle Creek Rd (-0.1 miles) to I-69 92.0 to 108.2 Medium Various lanes closed 3/20/15 1:00 PM to 11/28/15 1:00 PM MDOT

I-94 Express EB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
26th St to 69th St 54.1 to 59.5 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:00 AM to 1:30 PM IDOT Moving Operation

I-94 Express WB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
69th St to 26th St 59.5 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation

I-94 WB (Regional)
Location Mile Marker Severity Closure Details Time Periods Source Description
I-69 to Climax And Battle Creek Rd (+0.1 miles) 108.2 to 92.0 Medium Various lanes closed 3/20/15 1:00 PM to 11/28/15 1:00 PM MDOT
Exit ramp to EB Cork St 80.0 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Exit ramp to Cork St 80.0 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
at Cork St 79.9 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Entrance ramp from NB Sprinkle Rd 79.7 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Entrance ramp from NB Sprinkle Rd 79.7 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Entrance ramp from SB Sprinkle Rd 79.4 Medium Various lanes closed 3/16/15 7:00 AM to 11/15/15 7:00 PM MDOT Bridge Reconstruction
Entrance ramp from SB Sprinkle Rd 79.4 Medium All lanes and shoulders closed 3/16/15 6:00 AM to 11/30/15 5:00 PM MDOT Bridge Work; Sprinkle Road will have one lane open in each direction between Cork Street and MidLink Drive during construction, expect delays.
More information
Entrance ramp from WB I-80 15.3 Major All lanes and shoulders closed 3/18/15 7:00 AM to 4/5/15 11:59 PM Indiana Toll Road Lake Station exit ramp closed for Ramp Demo/Rebuild ***Long Term***
IN State Line to Bishop Ford Fwy (IL-394) Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 9:30 AM to 2:30 PM IDOT Moving Operation
I-80 to NB Stony Island Feeder Exit 74.5 to 65.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 2:00 PM IDOT Moving Operation
NB Stony Island Feeder Exit to Dan Ryan Expy (I-94) / I-57 65.7 to 62.9 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:30 AM to 1:00 PM IDOT Moving Operation
Marquette Rd (67th St) to 63rd St 59.3 to 58.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
63rd St to 57th St 58.7 to 58.0 Medium Right lane and right shoulder closed, two lanes open 4/1/15 10:00 AM to 2:00 PM IDOT
Garfield Blvd (55th St) to 26th St 57.7 to 54.1 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 3:00 PM IDOT Moving Operation
26th St to Stevenson Expy (I-55) 54.1 to 53.7 Medium Left lane or right lane and both shoulders closed with partial ramp closures 4/1/15 10:00 AM to 1:00 PM IDOT Moving Operation
Stevenson Expy (I-55) to Eisenhower Expy (I-290) 53.7 to 51.7 Medium Right lane and right shoulder closed, two to four lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from NB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from SB Stevenson / I-55 53.0 Minor Right shoulder closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to EB I-290 52.4 Major All lanes and shoulders closed 3/13/15 12:00 AM to 12/31/16 11:59 PM IDOT ***Long Term Closure***
Exit ramp to WB I-290 52.4 Minor Both shoulders closed, all lanes open 3/12/15 12:00 AM to 6/1/16 11:59 PM IDOT Reduced width ***Long Term Closure***
Roosevelt Rd to Eisenhower Expy (I-290) 52.2 to 51.7 Minor Both shoulders closed, all lanes open 3/13/15 12:00 AM to 6/1/16 11:59 PM IDOT Lanes shifted. 4 lanes total through section. ***Long Term Closure***
Entrance ramp from Roosevelt Rd 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Entrance ramp from Taylor St 51.8 Medium All lanes and shoulders closed 3/11/15 12:00 AM to 6/1/16 11:59 PM IDOT ***Long Term Closure***
Eisenhower Expy (I-290) to Jackson Blvd 51.7 to 51.5 Minor Both shoulders closed, all lanes open 10/13/14 12:00 AM to 7/31/15 11:59 PM IDOT Traffic weaved ***Long Term Closure***
Eisenhower Expy (I-290) to I-190 51.7 to 79.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Grand Ave to Ohio Feeder 50.5 to 50.4 Minor Right shoulder closed, all lanes open 4/1/15 9:00 AM to 3:00 PM IDOT
Kennedy Junction to Park Ave West 43.5 to 23.1 Minor Both shoulders closed, all lanes open with partial ramp closures 4/1/15 9:00 AM to 3:00 PM IDOT Moving Operation
Exit ramp to EB IL-132 8.8 Minor Partial closure 3/20/15 7:00 AM to 5/1/15 11:59 PM Illinois Tollway Rdwy Reconst. and Plaza Repairs;Left Side of Ramp Closed; *** Long Term Closure ***
Entrance ramp from EB IL-132 8.6 Major All lanes and shoulders closed 2/27/15 7:00 AM to 5/19/15 11:59 PM Illinois Tollway Entrance Ramp Closed; *** Long Term Closure ***
Entrance ramp from WB IL-132 8.8 Minor Partial closure 3/11/15 6:00 AM to 4/17/15 11:59 PM Illinois Tollway Right Side of Ramp Closed; *** Long Term Closure ***
at Old Highway 11 334.9 Minor Right lane closed, two lanes open 3/12/15 12:00 AM to 11/25/15 11:45 PM WisDOT Construction - N-S FREEWAY, STH 20 INTERCHANGE | MAINLINE & RAMPS | I 94 | RACINE
at WI-20 333.1 Medium Right lane closed, two lanes open 3/12/15 6:00 AM to 11/30/15 11:59 AM WisDOT *** Long Term Closure ***
Exit ramp to EB Howard Ave 315.2 Medium All lanes and shoulders closed 2/15/15 12:00 AM to 8/31/15 11:45 PM WisDOT Construction - Detour: Exit to Holt Ave and follow posted detour
Exit ramp to EB Lapham Blvd 313.0 Medium All lanes and shoulders closed 1/12/15 12:00 AM to 9/30/15 11:45 PM WisDOT Construction - Detour: Use alt route (continue north on 4th St to Lapham Blvd)
Exit ramp to NB 34th St 308.5 Medium All lanes and shoulders closed 4/1/15 11:00 AM to 2:00 PM WisDOT Maintenance - Detour: Use Alt. Route
64th St to WI-181 (+0.2 miles) 306.6 to 305.1 Medium Left lane closed, two lanes open 12/6/14 12:00 AM to 12/5/15 11:45 PM WisDOT Construction - ZOO IC, ZOO INTERCHANGE PHASE 1 | LINCOLN - BLUEMOUND, 121ST - 70TH | USH 45 | MILWAUKEE
Exit ramp to WB Oconnor St 305.5 Medium All lanes and shoulders closed 10/13/14 12:00 AM to 5/22/15 11:45 PM WisDOT Construction - Detour: Take 68th-70th st exit, continue W on O'Conner, North on 76th st, West on Bluemound to 84th st (North 84th st Detour). Take 68th-70th exit, Continue West, South on 70th, West on Greenfield to 84th st. (South 84th st Detour).
Exit ramp to NB US-45 304.6 Major All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 4:30 AM WisDOT Construction - Detour: Take I-94 WB to the 68th Exit to 76th to Bluemound to Glenview to Watertown Plank to the US45 North Ramp.
Exit ramp to EB I-894 304.6 Major All lanes and shoulders closed 3/9/15 12:00 AM to 8/26/17 11:45 PM WisDOT Construction - Detour: I-94 to 70th St to Greenfield to the I-894/US 45 South Ramp And I-94 to HWY 100 to Greenfield to the I-894/US 45 South Ramp And I-94 to Moorland to Greenfield to the I-894/US 45 South Ramp
Entrance ramp from SB US-45 304.2 Major All lanes and shoulders closed 3/25/15 10:00 PM to 4/2/15 4:30 AM WisDOT Construction - Detour: Take US45 South to Watertown Plank to HWY 100 to the I-94 West Ramp. OR US45 South to Greenfield to HWY 100 to the I94 West Ramp.
CR-J (+0.1 miles) to Kent Rd 115.5 to 114.3 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

I-39 NB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
CR-J (+0.1 miles) to Kent Rd 115.5 to 114.3 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

I-39 SB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Black Rd (+0.4 miles) to CR-J (-0.2 miles) 113.9 to 115.5 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

I-43 NB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
WI-11 (-0.2 miles) to WI-11 (+0.3 miles) 28.1 to 28.6 Medium Right lane closed, one lane open 3/30/15 6:00 AM to 4/10/15 3:00 PM WisDOT Construction - ROCK FREEWAY SB | USH 12 - STH 83 | I 43 | WALWORTH
Stone School Rd to WI-83 (+0.5 miles) 42.1 to 43.6 Medium Left lane closed, one lane open 3/27/15 5:00 AM to 4/10/15 5:00 PM WisDOT Construction - ROCK FREEWAY SB | USH 12 - STH 83 | I 43 | WALWORTH
Exit ramp to EB Howard Ave 315.2 Medium All lanes and shoulders closed 2/15/15 12:00 AM to 8/31/15 11:45 PM WisDOT Construction - Detour: Exit to Holt Ave and follow posted detour
Exit ramp to EB Lapham Blvd 313.0 Medium All lanes and shoulders closed 1/12/15 12:00 AM to 9/30/15 11:45 PM WisDOT Construction - Detour: Use alt route (continue north on 4th St to Lapham Blvd)
Exit ramp to SB Port Washington Rd 76.8 Medium All lanes and shoulders closed 4/1/15 11:30 AM to 4:30 PM WisDOT Maintenance - Detour: Use Alt. Route

I-43 SB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Canal St to National/WI-59 310.9 to 311.5 Minor Right shoulder closed, all lanes open 3/24/15 9:00 AM to 5/15/15 11:59 PM WisDOT Long term closure until mid May 2015; *** Long Term Closure ***
Ramp from SB I-43 to National Ave 311.3 Minor Left shoulder closed, all lanes open 3/24/15 9:00 AM to 5/15/15 11:59 PM WisDOT Long term closure until mid May 2015; *** Long Term Closure ***
at Lincoln Ave 313.0 Major Right two lanes closed, one lane open 3/31/15 9:30 PM to 4/1/15 5:30 PM WisDOT
Edgewood Ave (+1.1 miles) to Stone School Rd 44.3 to 42.1 Medium Left lane closed, one lane open 3/27/15 5:00 AM to 4/10/15 5:00 PM WisDOT Construction - ROCK FREEWAY SB | USH 12 - STH 83 | I 43 | WALWORTH
WI-11 (-0.3 miles) to WI-11 (+0.2 miles) 28.7 to 28.2 Medium Left lane closed, one lane open 3/30/15 6:00 AM to 4/10/15 3:00 PM WisDOT Construction - ROCK FREEWAY SB | USH 12 - STH 83 | I 43 | WALWORTH

I-90 EB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Black Rd (+0.4 miles) to CR-J (-0.2 miles) 113.9 to 115.5 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

I-90 WB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
CR-J (+0.1 miles) to Kent Rd 115.5 to 114.3 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

I-94 EB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Black Rd (+0.4 miles) to CR-J (-0.2 miles) 113.9 to 115.5 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA
WI-100 (-0.2 miles) to I-894 303.5 to 304.3 Major All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 5:00 AM WisDOT Construction - Detour: Take I-94 EB to HWY 100 to Greenfield to US 45 North to I-94 EB. OR Take I-94 EB to HWY 100 to Watertown Plank to US45 NB.
Canal St to National/WI-59 310.9 to 311.5 Minor Right shoulder closed, all lanes open 3/24/15 9:00 AM to 5/15/15 11:59 PM WisDOT Long term closure until mid May 2015; *** Long Term Closure ***
Ramp from SB I-43 to National Ave 311.3 Minor Left shoulder closed, all lanes open 3/24/15 9:00 AM to 5/15/15 11:59 PM WisDOT Long term closure until mid May 2015; *** Long Term Closure ***
at Lincoln Ave 313.0 Major Right two lanes closed, one lane open 3/31/15 9:30 PM to 4/1/15 5:30 PM WisDOT
Entrance ramp from SEB WI-100 323.1 Major All lanes and shoulders closed 3/23/15 12:00 AM to 5/22/15 11:45 PM WisDOT Construction - Detour: Take HWY 100 South to Greenfield to I-894/US45 North to 94 East. OR Take HWY 100 North to Watertown Plank to Glenview to I-94 East
50th Rd to 58th Rd 331.9 to 334.9 Medium Various lanes closed 3/20/15 12:00 AM to 11/25/15 11:45 PM WisDOT Construction - N-S FREEWAY, STH 20 INTERCHANGE | MAINLINE & RAMPS | I 94 | RACINE
Exit ramp to WB WI-20 332.7 Major All lanes and shoulders closed 3/20/15 12:00 AM to 7/2/15 11:45 PM WisDOT Construction - Detour: Use I-94 EB (SB) to County K to West Frontage Road to WIS 20; *** Long Term Closure ***
at WI-20 333.1 Medium Right lane closed, two lanes open 3/21/15 8:00 AM to 11/30/15 11:59 PM WisDOT *** Long Term Closure ***
Entrance ramp from EB WI-20 332.7 Major All lanes and shoulders closed 3/20/15 12:00 AM to 11/24/15 11:45 PM WisDOT Construction - Detour: Use WIS 20 to West Frontage Road to 58th Road to West Frontage Road to WIS 11 to I-94 EB (SB); *** Long Term Closure ***

I-94 WB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
at Old Highway 11 334.9 Minor Right lane closed, two lanes open 3/12/15 12:00 AM to 11/25/15 11:45 PM WisDOT Construction - N-S FREEWAY, STH 20 INTERCHANGE | MAINLINE & RAMPS | I 94 | RACINE
at WI-20 333.1 Medium Right lane closed, two lanes open 3/12/15 6:00 AM to 11/30/15 11:59 AM WisDOT *** Long Term Closure ***
Exit ramp to EB Howard Ave 315.2 Medium All lanes and shoulders closed 2/15/15 12:00 AM to 8/31/15 11:45 PM WisDOT Construction - Detour: Exit to Holt Ave and follow posted detour
Exit ramp to EB Lapham Blvd 313.0 Medium All lanes and shoulders closed 1/12/15 12:00 AM to 9/30/15 11:45 PM WisDOT Construction - Detour: Use alt route (continue north on 4th St to Lapham Blvd)
Exit ramp to NB 34th St 308.5 Medium All lanes and shoulders closed 4/1/15 11:00 AM to 2:00 PM WisDOT Maintenance - Detour: Use Alt. Route
64th St to WI-181 (+0.2 miles) 306.6 to 305.1 Medium Left lane closed, two lanes open 12/6/14 12:00 AM to 12/5/15 11:45 PM WisDOT Construction - ZOO IC, ZOO INTERCHANGE PHASE 1 | LINCOLN - BLUEMOUND, 121ST - 70TH | USH 45 | MILWAUKEE
Exit ramp to WB Oconnor St 305.5 Medium All lanes and shoulders closed 10/13/14 12:00 AM to 5/22/15 11:45 PM WisDOT Construction - Detour: Take 68th-70th st exit, continue W on O'Conner, North on 76th st, West on Bluemound to 84th st (North 84th st Detour). Take 68th-70th exit, Continue West, South on 70th, West on Greenfield to 84th st. (South 84th st Detour).
Exit ramp to NB US-45 304.6 Major All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 4:30 AM WisDOT Construction - Detour: Take I-94 WB to the 68th Exit to 76th to Bluemound to Glenview to Watertown Plank to the US45 North Ramp.
Exit ramp to EB I-894 304.6 Major All lanes and shoulders closed 3/9/15 12:00 AM to 8/26/17 11:45 PM WisDOT Construction - Detour: I-94 to 70th St to Greenfield to the I-894/US 45 South Ramp And I-94 to HWY 100 to Greenfield to the I-894/US 45 South Ramp And I-94 to Moorland to Greenfield to the I-894/US 45 South Ramp
Entrance ramp from SB US-45 304.2 Major All lanes and shoulders closed 3/25/15 10:00 PM to 4/2/15 4:30 AM WisDOT Construction - Detour: Take US45 South to Watertown Plank to HWY 100 to the I-94 West Ramp. OR US45 South to Greenfield to HWY 100 to the I94 West Ramp.
CR-J (+0.1 miles) to Kent Rd 115.5 to 114.3 Major Right two lanes closed, one lane open 3/26/15 12:00 AM to 4/19/15 11:45 PM WisDOT Construction - Madison - Portage | Rowan Creek Bridges | I 39 | COLUMBIA

I-794 EB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
4th St to Lincoln Memorial Dr 0.4 to 3.1 Medium Right lane closed, two lanes open 12/11/13 12:00 AM to 11/1/15 11:45 PM WisDOT Construction - HOAN BRIDGE & LAKE FREEWAY | MILWAUKEE RIVER - CARFERRY DR | I 794 | MILWAUKEE
Exit ramp to SB Jackson St 0.8 Medium All lanes and shoulders closed 12/5/14 12:00 AM to 9/30/15 11:45 PM WisDOT Construction - Detour: Traffic uses Plankinton or St. Paul James Lovell

I-794 WB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
south of Hoan Bridge arches to Lincoln Memorial Dr 11.1 to 11.3 Medium Right lane closed, two lanes open 4/1/15 10:00 AM to 2:00 PM WisDOT
Carferry Dr to Harbor Dr 11.1 to 13.2 Major All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 5:00 AM daily until 4/4/15 WisDOT Construction - Detour: Detour Becher St. to I-43 NB
Entrance ramp from NWB Carferry Dr 11.3 Medium All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 5:00 AM daily until 4/4/15 WisDOT Construction - Detour: Detour Becher St. to I-43 NB
Polk St (-0.4 miles) to Polk St (-0.2 miles) 12.5 to 12.8 Medium Right lane closed, two lanes open 4/1/15 10:00 AM to 2:00 PM daily until 4/3/15 WisDOT Construction - HOAN BRIDGE & LAKE FREEWAY | MILWAUKEE RIVER - CARFERRY DR | I 794 | MILWAUKEE
Polk St (-0.4 miles) to Polk St (-0.2 miles) 12.5 to 12.8 Medium Right lane closed, two lanes open 4/1/15 7:30 PM to 4/2/15 6:00 AM daily until 4/4/15 WisDOT Construction - HOAN BRIDGE & LAKE FREEWAY | MILWAUKEE RIVER - CARFERRY DR | I 794 | MILWAUKEE
Exit ramp to NB Milwaukee ST 13.5 Medium All lanes and shoulders closed 12/21/13 12:00 AM to 11/1/15 11:45 PM WisDOT Construction - Detour: Downtown Traffic to Exit at Lincoln Memorial Drive

I-894 EB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Watertown Plank Rd (-0.4 miles) to Schlinger Ave (-0.1 miles) Major All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 5:00 AM WisDOT Construction - Detour: Take US45 SB to Watertown Plank to HWY 100 to Greenfield to I-894/US45 SB OR Take US45 SB to North to HWY 100 to Greenfield to I-894/US45 SB

I-894 WB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Exit ramp to EB WI-59 1.3 Medium All lanes and shoulders closed 10/15/14 12:00 AM to 11/30/17 11:45 PM WisDOT Construction - Detour: Take Greenfield Exit West to 108th st, 108th st North to Bluemound (West Bluemound Detour). Take Greenfield East to 84th st, 84th st North to Bluemound. (East Bluemound Detour)

US-12 EB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Gammon Rd (+0.2 miles) to Todd Dr (-0.4 miles) Medium Various lanes closed 4/1/15 8:00 PM to 4/2/15 5:00 AM daily until 4/4/15 WisDOT Construction - MOUNT HOREB - MADISON | VERONA R - SEMINOLE HIGHWAY | USH 18 | DANE
Entrance ramp from SEB Schroeder Rd Minor Right lane closed, two lanes open 3/16/15 12:00 AM to 11/20/15 11:45 PM WisDOT Construction - MOUNT HOREB - MADISON | VERONA R - SEMINOLE HIGHWAY | USH 18 | DANE
Raymond Rd to Seminole Hwy (-0.3 miles) Medium Left lane closed, up to two lanes open 3/30/15 12:00 AM to 5/1/15 11:45 PM WisDOT Construction - MOUNT HOREB - MADISON | RAYMOND RD - MADISON BELTLINE | USH 18 | DANE
Raymond Rd to Seminole Hwy (+0.3 miles) Medium Left lane closed, up to two lanes open 4/1/15 9:00 AM to 3:00 PM daily until 4/3/15 WisDOT Construction - MOUNT HOREB - MADISON | RAYMOND RD - MADISON BELTLINE | USH 18 | DANE

US-12 WB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Raymond Rd to Seminole Hwy (+0.3 miles) Medium Left lane closed, up to two lanes open 4/1/15 9:00 AM to 3:00 PM daily until 4/3/15 WisDOT Construction - MOUNT HOREB - MADISON | RAYMOND RD - MADISON BELTLINE | USH 18 | DANE
Todd Dr (+0.2 miles) to Whitney Way (+0.1 miles) Medium Various lanes closed 4/1/15 8:00 PM to 4/2/15 5:00 AM daily until 4/4/15 WisDOT Construction - MOUNT HOREB - MADISON | VERONA R - SEMINOLE HIGHWAY | USH 18 | DANE
at Seminole Hwy (+0.3 miles) Medium Right two lanes closed, one lane open 4/1/15 10:00 PM to 4/2/15 5:00 AM WisDOT Maintenance - Bridge Repair

US-41 NB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
at Old Highway 11 334.9 Minor Right lane closed, two lanes open 3/12/15 12:00 AM to 11/25/15 11:45 PM WisDOT Construction - N-S FREEWAY, STH 20 INTERCHANGE | MAINLINE & RAMPS | I 94 | RACINE
at WI-20 333.1 Medium Right lane closed, two lanes open 3/12/15 6:00 AM to 11/30/15 11:59 AM WisDOT *** Long Term Closure ***
Exit ramp to EB Howard Ave 315.2 Medium All lanes and shoulders closed 2/15/15 12:00 AM to 8/31/15 11:45 PM WisDOT Construction - Detour: Exit to Holt Ave and follow posted detour
Exit ramp to EB Lapham Blvd 313.0 Medium All lanes and shoulders closed 1/12/15 12:00 AM to 9/30/15 11:45 PM WisDOT Construction - Detour: Use alt route (continue north on 4th St to Lapham Blvd)
Exit ramp to NB 34th St 308.5 Medium All lanes and shoulders closed 4/1/15 11:00 AM to 2:00 PM WisDOT Maintenance - Detour: Use Alt. Route

US-41 SB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Good Hope Rd (-0.1 miles) to Hampton Ave Medium Left lane closed, one or two lanes open 4/1/15 7:00 PM to 8:30 PM WisDOT Construction - Zoo Freeway | Burleigh St - Good Hope Rd | Ush 45 | MILWAUKEE
Canal St to National/WI-59 310.9 to 311.5 Minor Right shoulder closed, all lanes open 3/24/15 9:00 AM to 5/15/15 11:59 PM WisDOT Long term closure until mid May 2015; *** Long Term Closure ***
Ramp from SB I-43 to National Ave 311.3 Minor Left shoulder closed, all lanes open 3/24/15 9:00 AM to 5/15/15 11:59 PM WisDOT Long term closure until mid May 2015; *** Long Term Closure ***
at Lincoln Ave 313.0 Major Right two lanes closed, one lane open 3/31/15 9:30 PM to 4/1/15 5:30 PM WisDOT
Entrance ramp from SEB WI-100 323.1 Major All lanes and shoulders closed 3/23/15 12:00 AM to 5/22/15 11:45 PM WisDOT Construction - Detour: Take HWY 100 South to Greenfield to I-894/US45 North to 94 East. OR Take HWY 100 North to Watertown Plank to Glenview to I-94 East
50th Rd to 58th Rd 331.9 to 334.9 Medium Various lanes closed 3/20/15 12:00 AM to 11/25/15 11:45 PM WisDOT Construction - N-S FREEWAY, STH 20 INTERCHANGE | MAINLINE & RAMPS | I 94 | RACINE
Exit ramp to WB WI-20 332.7 Major All lanes and shoulders closed 3/20/15 12:00 AM to 7/2/15 11:45 PM WisDOT Construction - Detour: Use I-94 EB (SB) to County K to West Frontage Road to WIS 20; *** Long Term Closure ***
at WI-20 333.1 Medium Right lane closed, two lanes open 3/21/15 8:00 AM to 11/30/15 11:59 PM WisDOT *** Long Term Closure ***
Entrance ramp from EB WI-20 332.7 Major All lanes and shoulders closed 3/20/15 12:00 AM to 11/24/15 11:45 PM WisDOT Construction - Detour: Use WIS 20 to West Frontage Road to 58th Road to West Frontage Road to WIS 11 to I-94 EB (SB); *** Long Term Closure ***

US-45 NB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Exit ramp to EB WI-59 1.3 Medium All lanes and shoulders closed 10/15/14 12:00 AM to 11/30/17 11:45 PM WisDOT Construction - Detour: Take Greenfield Exit West to 108th st, 108th st North to Bluemound (West Bluemound Detour). Take Greenfield East to 84th st, 84th st North to Bluemound. (East Bluemound Detour)
Exit ramp to WB I-94 0.5 Major All lanes and shoulders closed 3/9/15 12:00 AM to 11/28/15 11:45 PM WisDOT Construction - Detour: I-894/US 45 to Beloit Rd to HWY 100 to the I-94 West Ramp. And I-894/US 45 to Greenfield to HWY 100 to the I-94 West Ramp. And US 45 North to Watertown Plank to HWY 100 to the I-94 West Ramp.
Entrance ramp from WB I-94 Major All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 4:30 AM WisDOT Construction - Detour: Take I-94 WB to the 68th Exit to 76th to Bluemound to Glenview to Watertown Plank to the US45 North Ramp.
Entrance ramp from WB Wisconsin Ave Medium All lanes and shoulders closed 10/3/14 12:00 AM to 12/31/16 11:45 PM WisDOT Construction - Detour: Wisconsin Ave to 97th St to Bluemound to HWY 100 to North Ave to USH 45 NB -- Wisconsin to 84th St to Watertown Plank Rd to USH 45 NB
Exit ramp to WB North Ave Medium All lanes and shoulders closed 4/2/15 9:00 AM to 2:00 PM WisDOT Maintenance - Detour: Use Alt Route
Burleigh St (-0.2 miles) to Hampton Ave Medium Right lane closed, two lanes open 4/1/15 7:00 PM to 9:30 PM daily until 4/2/15 WisDOT Construction - Zoo Freeway | Burleigh St - Good Hope Rd | Ush 45 | MILWAUKEE
Burleigh St (-0.2 miles) to Hampton Ave Major Right two lanes closed, one lane open 4/1/15 9:30 PM to 4/2/15 5:30 AM WisDOT Construction - Zoo Freeway | Burleigh St - Good Hope Rd | Ush 45 | MILWAUKEE

US-45 SB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Good Hope Rd (-0.1 miles) to Hampton Ave Medium Left lane closed, one or two lanes open 4/1/15 7:00 PM to 8:30 PM WisDOT Construction - Zoo Freeway | Burleigh St - Good Hope Rd | Ush 45 | MILWAUKEE
Entrance ramp from EB North Ave Medium All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 5:00 AM WisDOT Construction - Detour: Take North Ave East to HWY 100 to Greenfield to I-894/US45 South.
Watertown Plank Rd (-0.4 miles) to Schlinger Ave (-0.1 miles) Major All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 5:00 AM WisDOT Construction - Detour: Take US45 SB to Watertown Plank to HWY 100 to Greenfield to I-894/US45 SB OR Take US45 SB to North to HWY 100 to Greenfield to I-894/US45 SB
Entrance ramp from Watertown Plank Rd Medium All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 5:00 AM WisDOT Construction - Detour: Continue South on HWY 100 to Greenfield to I-894/US45 South.
Entrance ramp from Watertown Plank Rd Medium All lanes and shoulders closed 4/1/15 10:00 PM to 4/2/15 5:00 AM WisDOT Construction - Detour: Continue West to HWY 100 to Greenfield to I-894/US45 South.
Exit ramp to SB 94th St Medium All lanes and shoulders closed 10/15/14 12:00 AM to 12/31/16 11:45 PM WisDOT Construction - Detour: USH 45 to North Ave to HWY 100 to Wisconsin
Entrance ramp from WB Wisconsin Ave Medium All lanes and shoulders closed 11/19/14 12:00 AM to 11/1/16 11:45 PM WisDOT Construction - Detour: Take HWY 100 to Watertown Plank to the US45 SB Entrance Ramp. OR Take Glenview to Watertown Plank to the US45 SB Entrance Ramp
Exit ramp to WB I-94 0.1 Major All lanes and shoulders closed 3/25/15 10:00 PM to 4/2/15 4:30 AM WisDOT Construction - Detour: Take US45 South to Watertown Plank to HWY 100 to the I-94 West Ramp. OR US45 South to Greenfield to HWY 100 to the I94 West Ramp.
Entrance ramp from WB I-94 0.3 Major All lanes and shoulders closed 3/9/15 12:00 AM to 8/26/17 11:45 PM WisDOT Construction - Detour: I-94 to 70th St to Greenfield to the I-894/US 45 South Ramp And I-94 to HWY 100 to Greenfield to the I-894/US 45 South Ramp And I-94 to Moorland to Greenfield to the I-894/US 45 South Ramp

WI-16 EB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
Brown St (-0.5 miles) to Sawyer Rd Major Left lane closed, two lanes open 3/16/15 12:00 AM to 6/26/15 11:45 PM WisDOT Construction - OCONOMOWOC - WAUKESHA | STH 67 - I 94 | STH 16 | WAUKESHA

WI-16 WB (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
CR-JK (-0.3 miles) to CR-JK (+0.3 miles) Major Left lane closed, two lanes open 4/2/15 6:00 AM to 2:00 PM daily until 4/3/15 WisDOT Construction - OCONOMOWOC - WAUKESHA | STH 67 - I 94 | STH 16 | WAUKESHA
Sawyer Rd (-0.2 miles) to Brown St (+0.5 miles) Major Left lane closed, two lanes open 3/16/15 12:00 AM to 6/26/15 11:45 PM WisDOT Construction - OCONOMOWOC - WAUKESHA | STH 67 - I 94 | STH 16 | WAUKESHA

Columbia County (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
NB WI-73 from US-151 (-0.1 miles) to US-151 (+0.1 miles) Major All lanes closed and both shoulders open 3/30/15 7:00 AM to 4/6/15 12:00 PM WisDOT Construction - I 94 - COLUMBUS | USH 151 S JCT INTERCHANGE AREA | STH 73 | COLUMBIA
SB WI-73 from US-151 (-0.3 miles) to US-151 (+0.2 miles) Major All lanes closed and both shoulders open 3/30/15 7:00 AM to 4/6/15 12:00 PM WisDOT Construction - I 94 - COLUMBUS | USH 151 S JCT INTERCHANGE AREA | STH 73 | COLUMBIA

Dane County (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB US-14 from Market St to CR-P Major All lanes and shoulders closed 3/30/15 12:00 AM to 10/16/15 11:45 PM WisDOT Construction - Detour: County KP to Bourbon Street to County P to USH 14
WB US-14 from CR-P to County Road Kp Major All lanes and shoulders closed 3/30/15 12:00 AM to 10/16/15 11:45 PM WisDOT Construction - Detour: CTH P to Bourbon Street to CTH KP to USH 14
NB US-151 from Raymond Rd (-0.1 miles) to Beltline Medium Various lanes closed 6/25/13 7:00 AM to 10/1/15 11:59 PM Gateway More information on the project.
SB US-151 from Beltline to Raymond Rd (+0.1 miles) Medium Various lanes closed 6/25/13 7:00 AM to 10/1/15 11:59 PM Gateway More information on the project.

Kenosha County (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
WB WI-50 at 184th Ave Medium Right lane closed, one lane open 4/1/15 7:00 AM to 3:00 PM daily until 4/2/15 WisDOT Maintenance - Ditch repair
NB WI-83 at Wilmot Rd Minor All lanes and shoulders closed 4/1/15 7:00 AM to 3:00 PM daily until 4/3/15 WisDOT Permit - Full Lane Closure to remove overhead Utility Wires - traffic restricted each way:::flagging operation

Milwaukee County (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB US-18 from 103rd St to 99th St Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 4/30/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
EB US-18 from 97th St to 95th St Medium All lanes and shoulders closed 10/16/14 12:00 AM to 5/22/15 11:45 PM WisDOT Construction - Detour: Take 108th st SB to Greenfield, Greenfield EB to 84th st, 84th NB to Kearney, Kearney EB to 76th st, 76th NB to Bluemound.
WB US-18 from 44th St to WI-181 Medium Right lane closed, two lanes open 4/1/15 9:00 AM to 3:00 PM daily until 4/3/15 WisDOT Permit - Replace 15x10 concrete panel at 81st & bluemound
WB US-18 from 95th St to 97th St Medium All lanes and shoulders closed 10/16/14 12:00 AM to 5/22/15 11:45 PM WisDOT Construction - Detour: Take 84th st NB to WTP, WTP WB to 108th st, 108th st SB to Bluemound.
WB US-18 from 99th St to 103rd St Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 4/30/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
NB WI-38 from Oakwood Rd to Joseph M Hutsteiner Dr Medium Various lanes closed 4/1/15 12:00 AM to 4/2/15 12:00 AM daily until 7/4/15 WisDOT Construction - Detour: For nighttime ramp work by the airport TBD.
SB WI-38 from Joseph M Hutsteiner Dr to Oakwood Rd Medium Various lanes closed 4/1/15 12:00 AM to 4/2/15 12:00 AM daily until 7/4/15 WisDOT Construction - Detour: For nighttime ramp work by the airport TBD
EB WI-59 at 92nd St Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
EB WI-59 at WI-181 Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
EB WI-59 from 31st St to Layton Blvd Major Various lanes closed 4/1/15 9:00 AM to 2:00 PM daily until 4/2/15 WisDOT Permit - Install duct and fiber optic cable from Level3
EB WI-59 at I-43 Medium Various lanes closed 3/17/15 7:00 PM to 4/4/15 7:00 AM WisDOT Single lane closures. Traffic will be bi-directional on current Eastbound lanes of National Ave.
WB WI-59 at I-43 Medium Various lanes closed 3/17/15 7:00 PM to 4/4/15 7:00 AM WisDOT Single lane closures. Traffic will be bi-directional on current Eastbound lanes of National Ave.
WB WI-59 at WI-181 Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
WB WI-59 at 92nd St Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
NWB WI-100 from WI-38 to WI-241 Medium Various lanes closed 3/23/15 9:00 AM to 5/8/15 5:00 PM WisDOT Construction - RYAN RD | 27TH ST - STH 38 | STH 100 | MILWAUKEE
NWB WI-100 from Mitchell St to WI-59 Medium Various lanes closed 4/1/15 10:00 AM to 4:00 PM daily until 5/29/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
NWB WI-100 at Theodore Trecker Way Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
NWB WI-100 from Armour Ave to Howard Ave Medium Right lane closed, two lanes open 3/23/15 5:00 AM to 4/3/15 5:00 AM WisDOT Construction - Sth 100 | Sth 100 & Coldspring Intersection | Sth 100 | MILWAUKEE
SEB WI-100 from Howard Ave to Armour Ave Medium Right lane closed, two lanes open 4/1/15 5:00 AM to 4/2/15 5:00 AM daily until 4/4/15 WisDOT Construction - Sth 100 | Sth 100 & Coldspring Intersection | Sth 100 | MILWAUKEE
SEB WI-100 at Theodore Trecker Way Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
SEB WI-100 from WI-59 to Mitchell St Medium Various lanes closed 4/1/15 10:00 AM to 4:00 PM daily until 5/29/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
SEB WI-100 from WI-241 to WI-38 Medium Various lanes closed 3/23/15 9:00 AM to 4/3/15 5:00 PM WisDOT Construction - RYAN RD | 27TH ST - STH 38 | STH 100 | MILWAUKEE
NB WI-181 at WI-59 Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
NB WI-181 at Schlinger Ave Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
NB WI-181 from I-94 to Oconnor St Medium Various lanes closed 2/2/15 12:00 AM to 12/14/15 11:45 PM WisDOT Single Lane Closure; Construction - ZOO IC, ZOO INTERCHANGE PHASE 1 | LINCOLN - BLUEMOUND, 121ST - 70TH | USH 45 | MILWAUKEE
SB WI-181 from Honey Creek Pky (+0.1 miles) to I-94 Medium Various lanes closed 2/2/15 12:00 AM to 12/14/15 11:45 PM WisDOT Single Lane Closure; Construction - ZOO IC, ZOO INTERCHANGE PHASE 1 | LINCOLN - BLUEMOUND, 121ST - 70TH | USH 45 | MILWAUKEE
SB WI-181 at Schlinger Ave Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
SB WI-181 at WI-59 Medium Various lanes closed 4/1/15 9:00 AM to 3:00 PM daily until 5/31/15 WisDOT Construction - ZOO IC, 2014 TMP PROJECTS | VARIOUS LOCATIONS | VARIOUS HWY | MILWAUKEE
SB WI-794 at Pennsylvania Ave (-0.1 miles) Major Left lane closed, two lanes open 4/1/15 9:00 AM to 12:00 PM WisDOT Maintenance - Light Pole Repair
EB Lincoln Ave from Bay St to Lincoln Memorial Dr Minor Both shoulders closed, all lanes open 3/26/15 9:00 AM to 4/2/15 5:00 PM WisDOT Shoulder Closure; *** Long Term Closure ***
WB Lincoln Ave from Lincoln Memorial Dr to Bay St Minor Both shoulders closed, all lanes open 3/26/15 9:00 AM to 4/2/15 5:00 PM WisDOT Shoulder Closure; *** Long Term Closure ***

Racine County (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
WB WI-20 from Mealy Rd to WI-36 Medium Various lanes closed 4/1/15 7:30 AM to 3:00 PM daily until 4/3/15 WisDOT Maintenance - Pavement Repair

Walworth County (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
EB WI-11 from I-43 (-0.3 miles) to Newman Dr (-0.1 miles) Medium Left lane closed, one lane open 3/26/15 3:00 PM to 4/10/15 3:00 PM WisDOT Construction - ROCK FREEWAY SB | USH 12 - STH 83 | I 43 | WALWORTH
WB WI-11 from Newman Dr (-0.1 miles) to I-43 (+0.3 miles) Medium Left lane closed, up to one lanes open 3/26/15 3:00 PM to 4/10/15 3:00 PM WisDOT Construction - ROCK FREEWAY SB | USH 12 - STH 83 | I 43 | WALWORTH

Waukesha County (Wisconsin)
Location Mile Marker Severity Closure Details Time Periods Source Description
NB WI-67 from Armour Rd to WI-16 Medium Right lane closed, two lanes open 3/10/15 12:00 AM to 5/1/15 11:45 PM WisDOT Construction - OCONOMOWOC - WAUKESHA | STH 67 - I 94 | STH 16 | WAUKESHA
NEB WI-67 from I-94 to Old Tower Rd (-0.1 miles) Medium Right lane closed, two lanes open 4/1/15 9:00 AM to 3:00 PM daily until 4/3/15 WisDOT Construction - Summit Ave, City Oconomowoc | Delafield Rd - Summit Ave | Sth 67 | WAUKESHA
SB WI-67 from WI-16 (-0.1 miles) to Armour Rd Major Left lane closed, two lanes open 3/10/15 12:00 AM to 5/1/15 11:45 PM WisDOT Construction - OCONOMOWOC - WAUKESHA | STH 67 - I 94 | STH 16 | WAUKESHA

Site Contributors | Policies | Disclaimer | Glossary | Contact Us
Please send comments, suggestions, or requests for help to Travel Midwest webmaster.
Much of this site's functionality makes use of cookies and JavaScript.
Wed Apr 01 2015 09:26:01 CDT